Construction Updates,
June 2021.
Zenith & Zodiac - Complete OC received
Altis, Avior, Acrux - OC till 24th Floor
Atlas and Aura - OC till 20th floor
ZENITH
100%
ZODIAC
100%
ACRUX
95%
ALTIS
95%
ANTILIA
20%
ATLAS
95%
ATRIA
70%
AURA
95%
AVIOR
95%
ION
70%
TRITON
70%
VEGA
70%
CEDAR
35%
% mentioned above is the current demand due as per the construction linked payment schedule
TOWER | FLOOR DETAILS | DETAILED UPDATES |
---|---|---|
Zenith | Completed | OC received |
Zodiac | Completed | OC received |
Acrux | Completed work up to Terrace slab level | Part OC received till 24th floor
RCC work complete till terrace slab Flooring , Skirting , dado , kitchen platform, window roughground, toilet basin counter , plumbing work, water proofing , gypsumplaster, cement plaster, painting ,ms railing , Door frame ,Door shutter,door hardwares , Window , block work , flat alumium railing completed till the 31st floor Door & shutter polish completed till the 24th floor & single coat polish done on above floors. Cp & sanitary Flat completed till the 28th floor Stair case – flooring & skirting completed till B2 To 31st floors Stair case – window work completed till the terrace Lift lobby flooring , Dado, Architrave , plaster, painting , flase ceiling ,door ,window work completed till the 31st floor Entrance lobby work completed Society office work completed External Painting work completed till the 24 th floors & 25th to 31st 95% completed. Terrace water proofing completed & flooring work done 70% Concealed plumbing work completed from 1st to 31st floor Fire fighting Delivery material & installation work completed B2 to 31st floor Fire alarm work completed B2 to 31st floor. testing & commissioning completed Lift completed from B2 to 31st floor ( 4 nos ) |
Ion | Completed work up to Terrace slab level | RCC completed till terrace floor
Conceal Plumbing work 4th to 30th floor 100% completed & 31st floor work in progress , kitchen platform 4th to 31st floor completed 1st &2nd floor work in progress ,door frames 4th to 13th & 16th floor completed , 14th,15th, &17th work in progress, block work toilet 4th floor to 28th floor 100% completed, 29th ,30th ,31st,1st &2nd work in progress External painting putty, primer, texture base completed from basement 1 to terrace in flat 1 to 8 100% , final paint balance. Plumbing duct painting 80% and open duct work in progress Lift 100% completed basement to 31st floor Fire fighting installation 80% completed |
Avior | Completed work up to Terrace slab level | Part OC received till 24th Floor
RCC work complete till terrace slab Flat finishing work completed . Flooring , Skirting , dado , kitchen platform , window, toilet basin counter ,water proofing , gypsum plaster , cement plaster , painting , ms railing ,flat door frames this work done till the 31st floor Stair case work completed from b2 to 31st floor Entrance lobby work completed Lift lobby completed till the 31st floor & painting work completed till 24th floor & 25th to 31st floor 1 coat paint balance Refuge floor completed Stilt floor work completed Electrification service completed till 31st floor Plumbing service completed in flat & servant toilet work completed till the 24th floor. Fire fighting completed B2 to 31st floors & handover to facility Lift all completed from B2 to 31st |
Vega | Completed work up to Terrace slab level | RCC completed till terrace floor,
3rd floor to 30th floor conceal plumbing work completed 31st floor WIP Water proofing 3rd to 20th floor completed above floor WIP Block work 3rd to 30th floor completed External painting texture work 65% completed Lift 90% completed Fire fighting installation 80 % completed 1st to 31st floor & lower , upper, & stilt floor fire 80% completed balance work in progress Terrace water proofing 40% completed & balance work in progress |
Antilia | Excavation completed | Foundation work 70% completed , plinth slab at 98.8mm level 10 % completed. |
Aura | Completed work up to Terrace slab level | Part OC received till 20th floor
RCC work completed till terrace level Possession flat 61 done Flat finishing completed 100% 1st to 30th floor, flooring , kitchen platform , window , plumbing work , door fittings , flat aluminium railing Painting work 1st to 20th 100% completed 21st to 30th floor 2nd coat in progress External painting 1st to 30th floor 100% completed stilt painting 70% completed Lift 100% completed L1 , L2, L3,L4 – Lb to 30th floor |
Atlas | Completed work up to Terrace slab level | Part OC received till 20th floor
RCC completed till terrace floor Flat finishing completed 100% Possession flat – 71 done External paintaing 1st to 30th floor completed stilt paintaing 80 % completed, duct & duct pipe paintaing completed 100% Terrace water proofing completed & flooring work done 75% Concealed plumbing completed 100% Fire fighting installation b2 building from 1st to 30th floor completed B1 in progress Lift 100% completed Entrance lobby , society office , stair case , lift lobby completed 100% |
Triton | Substructure RCC work completed | UGWT RCC completed
Superstructure RCC work below OHT bottom slab work completed , Parapet wall completed |
Altis | Finishing work & RCC completed | RCC completed till terrace floor
Flat finishing work completed , Flooring,skirting, toilet flooring , toilet dado ,kitchen platform, window work completed till 100% , pplumbing work completed till 32nd floor 100% painting work done tiill 25th floor & 26th to 32nd floor 1st coat paint completed & 2 coat work in progress. Door frame fixing work completed till 32nd floor 100% completed Lift L1,L2.L3,L4 100% completed basement to 32nd floor Fire fighting installation done till 32nd floor ,Fire alarm & testing ,commissioning done till 25th floor & 26th to 32nd floor 80% work completed |
Cedar | Excavation completed | Substructure RCC work ground floor slab 103.75mm completed
UGWT completed Superstructure RCC work 1st floor slab completed except open well staircase area mivan setting for 1st floor flat no 5,6,7 IP |
Atria | RCC work completed | Substructure RCC work completed
UGWT , Superstructure RCC work , OHWT & LMR work completed |