Construction Updates,
March 2021.
Zenith & Zodiac - Complete OC received
Altis, Avior, Acrux - OC till 24th Floor
Atlas and Aura - OC till 20th floor
ZENITH
100%
ZODIAC
100%
ACRUX
80%
ALTIS
90%
ANTILIA
20%
ATLAS
80%
ATRIA
70%
AURA
80%
AVIOR
90%
ION
70%
TRITON
70%
VEGA
70%
CEDAR
20%
TOWER | FLOOR DETAILS | DETAILED UPDATES |
---|---|---|
Zenith | Completed | OC received |
Zodiac | Completed | OC received |
Acrux | Completed work up to Terrace slab level | Part oc received till 24th floor
RCC work complete till terrace slab 1st to 31st floor tiling completed Plumbing work in Completed upto 31st floor Final coat paint 1st to 24th floor completed Lift completed from B2 to 24th completed (3Nos), completed from B2 to 31st completed (1No) Door frame fixing work completed till 31st floor |
Ion | Completed work up to Terrace slab level | RCC completed till terrace floor
Conceal Plumbing completed up to 31st floor except 1st & 2nd floor, toilet water proofing complete upto 26th floor except 1st & 2nd floor, 75% external texture paint work completed Door frame fixing work initiated form 4th floor Kitchen Platform 3rd to 31st floor completed 3 lifts work completed ( L1, L2, & L4) |
Avior | Completed work up to Terrace slab level | Part OC received till 24th Floor
RCC work complete till terrace slab Internal Civil work completed Internal Tiling work completed upto 31st floor except 27th floor Toilet Conceal plumbing work completed upto 31st floor Toilet waterproofing work completed upto 31st floor Painting Completed B2 To 31st floor Firefighting B2 to 31st floors are completed All 4 lifts completed |
Vega | Completed work up to Terrace slab level | RCC completed till terrace floor,
3rd floor to 23th floor Conceal plumbing work completed expect 1st & 2nd Water proofing 3rd to 7th th Floor comleted 8th to 12th floor completed 1 lift is ready, 3 lift installation WIP External texture paint work has initiated |
Antilia | Foundation | Initiated work for foundation |
Aura | Completed work up to Terrace slab level | OC received till 20th floor
RCC work completed till terrace level Possession Done – 40 flats Water proofing 1st floor to 30th floor work completed (Toilets & Kitchens Sunk) 27th to 30th floor utility and flower bed WIP Tiling work Completed till 25th floor All finishing activity completed upto 25th floor Fire fighting, FAPA completed upto 30th floor 4 lifts work completed Conceal plumbing work completed till the 25th floor |
Atlas | Completed work up to Terrace slab level | OC received till 20th floor
Possession Done – 51 done RCC work completed till terrace level Tiling work Completed till 25th floor All finishing activity completed upto 20th floor Fire fighting, FAPA completed upto 30th floor L-1,L-2, and L-4 LB to 30th floor 100% completed. L3 WIIP Conceal plumbing work completed till the 25th floor |
Triton | Completed RCC work up to 30th Slab level | RCC work completed up to 30th Slab level
25th Slab in progress. Pour 1 casting done. Pour 2 and pour 3 WIP. |
Altis | Completed work up to Terrace slab level | 1st Floor to Terrace Floor RCC work completed (33rd Floor Slab)
Part OC received till 24th Floor Internal Civil work completed Internal Tiling work initiated form 30th floor Toilet waterproofing & conceal plumbing completed up to 31st floor All 4 lifts completed Entrance Lobby completed External Painting Completed |
Cedar | Excavation in progress | Substructure RCC work Ground Slap ( 103.75) completed |