Construction Updates,
September 2021.

Zenith & Zodiac - Complete OC received

Altis, Avior, Acrux - OC till 24th Floor

Atlas and Aura - OC till 20th floor

Phase 1

ZENITH 100%
ZODIAC 100%
ACRUX 95%
ALTIS 95%
ANTILIA
25%
ATLAS 95%
ATRIA 70%
AURA 95%
AVIOR 95%
ION 70%
TRITON 70%
VEGA 78%

Phase 2

CEDAR
35%
DAFFODIL
10%

% mentioned above is the current demand due as per the construction linked payment schedule

OC received

OC received

Completed work up to Terrace slab level

Part OC received till 24th floor

RCC work complete till terrace slab

Flooring , Skirting , dado , kitchen platform, window roughground, toilet basin counter , plumbing work, water proofing , gypsumplaster, cement plaster, painting ,ms railing , Door frame ,Door shutter,door hardwares , Window , block work , flat alumium railing completed till the 31st floor

Door & shutter polish completed till the 31st floor & single coat polish done on above floors.

Cp & sanitary Flat completed till the 31st floor

Stair case – flooring & skirting completed till B2 To 31st floors

Stair case – window work completed till the terrace

Lift lobby flooring , Dado, Architrave , plaster, painting , flase ceiling ,door ,window work completed till the 31st floor

Entrance lobby work completed

Society office work completed

External Painting work completed till the 24 th floors & 25th to 31st 95% completed.

Terrace water proofing completed & flooring work done 70%

Concealed plumbing work completed from 1st to 31st floor

Fire fighting Delivery material & installation work completed B2 to 31st floor

Fire alarm work completed B2 to 31st floor. testing & commissioning completed

Lift completed from B2 to 31st floor ( 4 nos )

Completed work up to Terrace slab level

RCC completed till terrace floor



Conceal Plumbing work 2nd to 31st floor 100% completed, kitchen platform 4th to 31st floor completed 1st & 2nd floor work in progress, door frames main door 1st to 31st and internal flat 2nd to 23rd floor completed and 1st to 21st floor WIP, block work toilet 1st to 31st floor 100% completed.

Painting 4th to 9th floor putty work completed & 10th floor WIP

Plumbing Duct & Open duct Painting-100% completed


Lift 100% completed basement to 31st floor


Fire fighting installation 100% completed

Completed work up to Terrace slab level

Part OC received till 24th Floor

RCC work complete till terrace slab

Flat finishing work completed . Flooring , Skirting , dado , kitchen platform , window, toilet basin counter ,water proofing , gypsum plaster , cement plaster , painting , ms railing ,flat door frames this work done till the 31st floor

Stair case work completed from b2 to 31st floor

Entrance lobby work completed

Lift lobby completed till the 31st floor & painting work completed till 31st floor

Refuge floor completed

Stilt floor work completed

Electrification service completed till 31st floor

Plumbing service completed in flat & servant toilet work completed till the 31st floor.

Fire fighting completed B2 to 31st floors & handover to facility

Lift all completed from B2 to 31st

Completed work up to Terrace slab level

RCC completed till terrace floor,

1st floor to 31st floor Conceal plumbing work completed 1st work in progress

Waterproofing 1st to 28th Floor completed and 29th floor WIP

3rd to 31st floor 100% completed (Ledge wall)

External painting texture work 80% completed

Lift 90% completed

Fire fighting installation 100% completed, plinth slab 100% completed, testing and commissioning 100% completed

Terrace water proofing 40% completed & balance work in progress

Excavation completed

Foundation work 100% completed, plinth slab 100% completed. UGWT 100% RCC Completed.

Completed work up to Terrace slab level

Part OC received till 20th floor

RCC work completed till terrace level

Possession flat 82 done

Flat finishing completed 100% 1st to 30th floor, flooring , kitchen platform , window , plumbing work , door fittings , flat aluminium railing

Painting work 1st to 30th 100% completed

External painting 1st to 30th floor 100% completed stilt painting 80% completed

Lift 100% completed L1 , L2, L3,L4 – Lb to 30th floor

Completed work up to Terrace slab level

Part OC received till 20th floor

RCC completed till terrace floor

Flat finishing completed 100%

Possession flat – 94 done

External painting 1st to 30th floor completed, ventilation 100% completed, stilt painting 80 % completed, duct & duct pipe painting completed 100%

Terrace water proofing completed & flooring work done 90%

Concealed plumbing completed 100%

Fire fighting installation B1 & b2 building from 1st to 30th floor completed

Lift 100% completed

Entrance lobby , society office , stair case , lift lobby completed 100%

Substructure RCC work completed

UGWT RCC completed

Superstructure RCC work below OHT bottom slab work completed , Parapet wall completed

Finishing work & RCC completed

RCC completed till terrace floor

Flat finishing work completed , Flooring, skirting, toilet flooring , toilet dado, kitchen platform, window work completed till 32nd floor, 100% painting work done till 25th floor and 26th to 32nd floor coat paint completed

Door frame fixing work completed till 32nd floor 100% completed

Lift L1,L2.L3,L4 100% completed basement to 32nd floor

Fire fighting installation done till 32nd floor ,Fire alarm & testing ,commissioning done till 25th floor & 26th to 32nd floor 100% work completed

Excavation completed

Substructure RCC work ground floor slab 103.75mm completed

UGWT completed

Superstructure RCC work 1st floor completed 2nd floor conventional area-100% completed, 3rd floor flat no. 4, 5, 6 completed

RCC work completed

Substructure RCC work completed

UGWT , Superstructure RCC work , OHWT & LMR work completed

Excavation completed

Footing completed

Column casting completed upto tie beam level

Column casting upto LG level is done 20%

Back-filling and levelling is in progress

UG tank pardi casted upto tie beam level. 2nd layer pardi reinforcement work is in progress

TOWER
FLOOR DETAILS
DETAILED UPDATES
Zenith
Completed
OC received
Zodiac
Completed
OC received
Acrux
Completed work up to Terrace slab level
Part OC received till 24th floor

RCC work complete till terrace slab

Flooring , Skirting , dado , kitchen platform, window roughground, toilet basin counter , plumbing work, water proofing , gypsumplaster, cement plaster, painting ,ms railing , Door frame ,Door shutter,door hardwares , Window , block work , flat alumium railing completed till the 31st floor

Door & shutter polish completed till the 31st floor & single coat polish done on above floors.

Cp & sanitary Flat completed till the 31st floor

Stair case – flooring & skirting completed till B2 To 31st floors

Stair case – window work completed till the terrace

Lift lobby flooring , Dado, Architrave , plaster, painting , flase ceiling ,door ,window work completed till the 31st floor

Entrance lobby work completed

Society office work completed

External Painting work completed till the 24 th floors & 25th to 31st 95% completed.

Terrace water proofing completed & flooring work done 70%

Concealed plumbing work completed from 1st to 31st floor

Fire fighting Delivery material & installation work completed B2 to 31st floor

Fire alarm work completed B2 to 31st floor. testing & commissioning completed

Lift completed from B2 to 31st floor ( 4 nos )
Ion
Completed work up to Terrace slab level
RCC completed till terrace floor



Conceal Plumbing work 2nd to 31st floor 100% completed, kitchen platform 4th to 31st floor completed 1st & 2nd floor work in progress, door frames main door 1st to 31st and internal flat 2nd to 23rd floor completed and 1st to 21st floor WIP, block work toilet 1st to 31st floor 100% completed

Painting 4th to 9th floor putty work completed & 10th floor WIP

Plumbing Duct & Open duct Painting-100% completed


Lift 100% completed basement to 31st floor


Fire fighting installation 100% completed
Avior
Completed work up to Terrace slab level
Part OC received till 24th Floor

RCC work complete till terrace slab

Flat finishing work completed . Flooring , Skirting , dado , kitchen platform , window, toilet basin counter ,water proofing , gypsum plaster , cement plaster , painting , ms railing ,flat door frames this work done till the 31st floor

Stair case work completed from b2 to 31st floor

Entrance lobby work completed

Lift lobby completed till the 31st floor & painting work completed till 31st floor

Refuge floor completed

Stilt floor work completed

Electrification service completed till 31st floor

Plumbing service completed in flat & servant toilet work completed till the 31st floor.

Fire fighting completed B2 to 31st floors & handover to facility

Lift all completed from B2 to 31st
Vega
Completed work up to Terrace slab level
RCC completed till terrace floor,

1st floor to 31st floor Conceal plumbing work completed 1st work in progress

Waterproofing 1st to 28th Floor completed and 29th floor WIP

3rd to 31st floor 100% completed (Ledge wall)

External painting texture work 80% completed

Lift 90% completed

Fire fighting installation 100% completed, plinth slab 100% completed, testing and commissioning 100% completed

Terrace water proofing 40% completed & balance work in progress
Antilia
Excavation completed
Foundation work 100% completed , plinth slab 100% completed. UGWT 100% RCC Completed
Aura
Completed work up to Terrace slab level
Part OC received till 20th floor

RCC work completed till terrace level

Possession flat 82 done

Flat finishing completed 100% 1st to 30th floor, flooring , kitchen platform , window , plumbing work , door fittings , flat aluminium railing

Painting work 1st to 30th 100% completed

External painting 1st to 30th floor 100% completed stilt painting 80% completed

Lift 100% completed L1 , L2, L3,L4 – Lb to 30th floor
Atlas
Completed work up to Terrace slab level
Part OC received till 20th floor

RCC completed till terrace floor

Flat finishing completed 100%

Possession flat – 94 done

External painting 1st to 30th floor completed, ventilation 100% completed, stilt painting 80 % completed, duct & duct pipe painting completed 100%

Terrace water proofing completed & flooring work done 90%

Concealed plumbing completed 100%

Fire fighting installation B1 & b2 building from 1st to 30th floor completed

Lift 100% completed

Entrance lobby , society office , stair case , lift lobby completed 100%
Triton
Substructure RCC work completed
UGWT RCC completed

Superstructure RCC work below OHT bottom slab work completed , Parapet wall completed
Altis
Finishing work & RCC completed
RCC completed till terrace floor

Flat finishing work completed , Flooring, skirting, toilet flooring , toilet dado, kitchen platform, window work completed till 32nd floor, 100% painting work done till 25th floor and 26th to 32nd floor coat paint completed

Door frame fixing work completed till 32nd floor 100% completed

Lift L1,L2.L3,L4 100% completed basement to 32nd floor

Fire fighting installation done till 32nd floor ,Fire alarm & testing ,commissioning done till 25th floor & 26th to 32nd floor 100% work completed
Cedar
Excavation completed
Substructure RCC work ground floor slab 103.75mm completed

UGWT completed

Superstructure RCC work 1st floor completed 2nd floor conventional area-100% completed, 3rd floor flat no. 4, 5, 6 completed
Atria
RCC work completed
Substructure RCC work completed

UGWT , Superstructure RCC work , OHWT & LMR work completed