Construction Updates, October 2022.
Construction Updates, October 2022.
Construction Progressing smoothly
Eminence construction is in full swing and we have completed work till terrace slab. We have already constructed the Rehab tower till 22nd floors. The Sale tower is set to replicate the same pace in terms of construction.
% mentioned above is the current demand due as per the construction linked payment schedule
Tower | Floor Details | Detailed Updates |
---|---|---|
Sale building | RCC work | Completed till terrace slab |
Blockwork | 2nd, 5th, 6th to 22nd floor completed | |
Gypsum work | 2nd, 6th, 7th to 22nd floor completed | |
Finishing work | Fire Fighting- 85% Conceal plumbing- 75% kitchen Platform- 65% waterproofing – 85% Lift 1 installation completed & Lift 2 in progress. |
|
Sample flat | Sample flat at 2nd floor completed | |
Rehab building | RCC work | RCC 100% completed |
Finishing work (completed up to 17th floor ) | Fire fighting- 100% Internal wall putty- 100% Conceal plumbing- 100% Door frame fixing- 100% Dado Tiling – 100% Flat flooring – 100% Kitchen platform- 100% Waterproofing – 100% Window fixing- 100% Lift installation – 100 % External painting – 100% Electrical internal wiring – 100% |
|
Infra | External Work | External paving work 80% completed. |