CONSTRUCTION UPDATES, AUGUST 2021

CONSTRUCTION UPDATES, AUGUST 2021

Completion
30%

% mentioned above is the current demand due as per the construction linked payment schedule

Floor Details Detailed Updates
Substructure RCC Work 100 % Completed
Superstructure RCC Work 100 % RCC 2nd Slab completed, 3rd slab 50 % completed.

Start typing and press Enter to search