CONSTRUCTION UPDATES, JANUARY 2022
Update as on 3rd January, 2022
CONSTRUCTION UPDATES, JANUARY 2022
Update as on 3rd January, 2022
Completion
% mentioned above is the current demand due as per the construction linked payment schedule
Floor Details | Detailed Updates |
---|---|
Substructure RCC Work | 100 % Completed |
Superstructure RCC Work | 100 % RCC 7th Slab completed, 8th slab 50 % completed. |
Shop Finishing -Block work | Ground floor shop blockwork 70% completed |