CONSTRUCTION UPDATES, March 2022
Update as on 2nd March, 2022
CONSTRUCTION UPDATES, March 2022
Update as on 4th March, 2022
Completion
% mentioned above is the current demand due as per the construction linked payment schedule
Floor Details | Detailed Updates |
---|---|
Substructure RCC Work | 100 % Completed |
Superstructure RCC Work | 100 % RCC 10th Slab completed, 11th slab work in progress. |
Shop Finishing -Block work | Ground floor shop blockwork 70% completed |