CONSTRUCTION UPDATES, January 2023
Update as on 4th January, 2023
CONSTRUCTION UPDATES,Jauary 2023
Update as on 4th January, 2023
Completion
% mentioned above is the current demand due as per the construction linked payment schedule
Floor Details | Detailed Updates |
---|---|
Substructure RCC Work | 100 % Completed |
Superstructure RCC Work | 100 % RCC 20th Slab completed & 21st RCC slab in progress. ( 70% completed) |
Shop Finishing -Block work | Ground floor shop block work 80% completed |
Common Area finishing work | Entrance lobby marble flooring 100% completed, Fire fighting double height Sprinkler & FAPA installation completed – 90% , Fire fighting 1st, 4th, 5th, 6th ,10th ,11th floor area completed. |