CONSTRUCTION UPDATES, February 2023

Update as on 2nd February, 2023

CONSTRUCTION UPDATES,February 2023

Update as on 2nd February, 2023

Completion
80%

% mentioned above is the current demand due as per the construction linked payment schedule

Floor Details Detailed Updates
Substructure RCC Work 100 % Completed
Superstructure RCC Work 100 % RCC 21st Slab completed & 22nd RCC slab in progress. ( 50% completed)
Shop Finishing -Block work Ground floor shop block work 80% completed
Common Area finishing work Entrance lobby marble flooring , Dado, Plaster, Electrical, Carpentry, Window, fire fighting double height Sprinkler & FAPA installation completed 100% , Fire fighting service 1st, 4th, 5th, 6th ,10th to 14th floor area completed. City lift 100% completed.