CONSTRUCTION UPDATES, December 2022
Update as on 4th December, 2022
CONSTRUCTION UPDATES, December 2022
Update as on 4th December, 2022
Completion
% mentioned above is the current demand due as per the construction linked payment schedule
Floor Details | Detailed Updates |
---|---|
Substructure RCC Work | 100 % Completed |
Superstructure RCC Work | 100 % RCC 19th Slab completed & 20th RCC slab in progress. ( 70% completed) |
Shop Finishing -Block work | Ground floor shop block work 80% completed |
Common Area finishing work | Entrance lobby marble flooring 90% completed, Fire fighting double height Sprinkler & FAPA installation completed – 90% , Fire fighting 1st, 4th, 5th, 6th floor area completed. |
MARATHON REFERRAL AND LOYALTY PROGRAM
MARATHON REFERRAL AND LOYALTY PROGRAM
Refer your friends to any Marathon property and get rewards worth 1% of your friend’s flat cost. Your friend gets a discount too. It’s a win-win.