CONSTRUCTION UPDATES, June 2023

Update as on 5th June, 2023

CONSTRUCTION UPDATES,June 2023

Update as on 5th June, 2023

Completion
80%

% mentioned above is the current demand due as per the construction linked payment schedule

Floor Details Detailed Updates
Substructure RCC Work 100 % Completed
Superstructure RCC Work 24th RCC Slab completed & 25th  RCC slab in progress. ( 50% completed)
Shop Finishing -Block work Ground floor shop block work 80% completed
Common area finishing work Entrance lobby completed .
Electrical panel installation completed .
Fire fighting services completed from floor 1st to 19th.
City lift installation 100% completed.