Construction Updates, June 2021

Construction Updates, June 2021

NeoSkies
26%
NeoHills
15%
NeoSquare
21%
NeoValley
20%

% mentioned above is the current demand due as per the construction linked payment schedule

Tower Floor Details Detailed Updates
NeoSkies – Rehab building RCC work RCC work of 13th floor is in progress – 50% done
Finishing work Blockwork completed till 10th floor starting from 4th floor
Plumbing Conceal work completed upto 8th floor starting from 4th floor
Gypsum work ip on 4th floor -80% completed
Water proofing ip on 4th floor – 50% completed
Electrical Conceal Work in block work completed upto 8th floor starting from 4th floor
Door Frame fixing work completed only on sample floor
Window rough ground marble fixing completed only on sample floor
Window sill fixing completed only on sample floor
Tiling & dado completed only on sample floor
Kitchen Platform fixing completed only on sample floor
Infra STP excavation ip – 70% done
NeoSkies – Sale building RCC work RCC work of 1st floor slab ip
NeoHills – Rehab building RCC work RCC work of 2nd floor slab in progress
NeoHills – Sale building RCC work Substructure work in progress including piling work- 70% done
NeoSquare – A wing RCC work Plinth completed, 1st slab work is in process
NeoSquare – B wing Ground to OHWT RCC completed
Flat Finishing Concealed plumbing completed
Kitchen platform, flooring, gypsum, door installation completed
Common area finishing Pending
Services Only fire fighting completed
NeoSquare – C wing RCC RCC of main building completed
PAP unit – extension flat at 4th floor level
Chajja casting for kitchen completed from Gr to 12th floor
Flat finishing Kitchen extension work at 4th floor is in progress, rest work is completed
Common area finishing Completed
Services Services of extra flat flat is pending rest is completed