% mentioned above is the current demand due as per the construction linked payment schedule
NeoSkies – Sale building
RCC work
Plinth 100% completed, 14th RCC slab completed & 15th RCC slab 20% completed.
Finishing work
Waterproofing in progress till 5th floor .
Conceal plumbing in progress till 5th floor.
Excavation 100 % completed.
NeoSkies – Rehab building
RCC work
23rd RCC slab completed.
Finishing work
Block work completed up to 20th floor
Plumbing work completed up to 20th floor
Gypsum work completed up to 20th floor
Waterproofing completed up to 20th floor
Flat flooring completed up to 19th floor
Electrical wiring done only on 15th floor
Lift installation in progress 80% completed.
External painting in progress .
Infra
Sewage Treatment Plant & Plain Cement Concrete- 100% completed, Raft 100% completed , wall casting 100% completed , Top slab casting 100% completed.
NeoHills – Sale building
RCC work
Substructure work 100% completed
Superstructure – 10th slab completed & 11th floor slab in progress.
NeoHills – Rehab building
RCC work
Pile, Excavation ,Substructure & Superstructure work 100% completed
NeoSquare – A wing
RCC work
7th slab casting completed & 8th slab reinforcement work in progress.
Flat Finishing
Blockwork finalized till 4th floor.
Gypsum plaster & electric concealed conducting work in process on 3rd floor.
NeoSquare – B wing
RCC work completed till top slab .
Flat Finishing
Concealed plumbing completed
Hall extension civil work , Flooring , Gypsum plaster work completed from 9th to 19th .
Staircase flooring is completed till terrace.
NeoSquare – C wing
RCC
RCC completed till top slab
Flat finishing
Kitchen extension work completed from 4th to 19th floor.
Concealed plumbing completed from 4th to 14th floor, waterproofing is completed from 4th to 10th floor. Kitchen platform & flooring work in progress.
Common area finishing
Completed
NeoValley
Construction not commenced yet
NeoPark
Construction not commenced yet
Tower | Floor Details | Detailed Updates |
---|---|---|
NeoSkies – Rehab building | RCC work | RCC work completed till 20th slab & 21st floor slab 5% completed |
Finishing work | Blockwork completed till 15th floor Plumbing Conceal work completed upto 15th floor Gypsum work completed upto 14th floor Water proofing completed upto 11th floor Flat flooring completed upto 4th floor |
|
Infra | STP pcc- 100% done, Raft r/f 100% completed , wall casting 60% completed , Top slab casting 20% completed. | |
NeoSkies – Sale building | RCC work | Plinth – 100% completed, 1st & 2nd Slab 100% completed, 3rd Slab completed till 30% . |
NeoHills – Rehab building | RCC work | Pile , Excavation & Substructure work 100% completed , Superstructure 15th slab work in progress. |
NeoHills – Sale building | RCC work | Substructure work 100% completed Superstructure 1st floor slab in progress. |
NeoSquare – A wing | RCC work | 2nd Slab completed |
NeoSquare – B wing | Ground to OHWT | RCC completed |
Flat Finishing | Concealed plumbing completed Kitchen platform, flooring, gypsum, door installation completed (till 16th floor) | |
Common area finishing | Gypsum on some of the floors completed | |
Services | Only fire fighting completed | |
NeoSquare – C wing | RCC | RCC of main building completed PAP unit – extension flat at 10th floor level Chajja casting completed. |
Flat finishing | Kitchen extension work at 9th floor is in progress Rest finishing inside the flat is completed | |
Common area finishing | Completed | |
Services | Services of extra flat(PAP unit flat No 7) is pending rest is completed |
Marathon Referral and Loyalty Program
Refer your friends to any Marathon property and get rewards worth 1% of your friend’s flat cost. Your friend gets a discount too. It’s a win-win.