Construction Updates,April 2023

Check updates:
NeoSkiesNeoHills
NeoSquareNeoValley

Update as on 2nd April, 2023

NeoSkies
73%
NeoHills
63%
NeoSquare
45%
NeoPark
20%
NeoValley, Kaveri
20%
NeoValley, Narmada
10%

% mentioned above is the current demand due as per the construction linked payment schedule

NeoSkies – Sale building

RCC work
Plinth 100% completed, 21st RCC slab 100% completed.

Finishing work
Waterproofing work in progress ( 67% completed)
Conceal plumbing work in progress ( 71% completed)
Gypsum work 85% completed .
Flat flooring work 61% completed.
Door shutter work in progress.

NeoSkies – Rehab building

RCC work
22nd RCC slab completed.

Finishing work
Block work completed up to 22nd floor
Plumbing work completed up to 22nd floor
Gypsum work completed up to 21st floor
Waterproofing completed up to 22nd floor
Lobby flooring completed up to 22nd floor.
Flat flooring completed up to 22nd floor.
Fire fighting flats completed up to 22nd floor.
Lift installation in progress .
External painting 100% completed.

Infra
Sewage Treatment Plant &  Plain Cement Concrete- 100% completed, Raft 100% completed , wall casting 100% completed , Top slab casting 100% completed.

NeoHills – Sale building

RCC work
Substructure work 100% completed
Superstructure – 22nd slab completed & 23rd floor slab in progress.

NeoHills – Rehab building

RCC work
Pile, Excavation ,Substructure &  Superstructure work 100% completed

NeoSquare – A wing

RCC work
14th slab casting completed & 15th beam & slab reinforcement work in progress.

Flat Finishing
Block work finalized till 8th floor & 9th floor work in progress.
Gypsum plaster & electric concealed conducting work in process on 8th floor.
Waterproofing & plumbing work in progress at 8th floor.
Tiling work & door frames work in progress.
Door frames making & fixing work in progress.

NeoSquare – B wing
RCC work completed till top slab .

Flat Finishing
Concealed plumbing completed
Hall extension civil work , Flooring , Gypsum plaster work completed from 9th to 19th .
Staircase flooring is completed from ground floor to till terrace.

NeoSquare – C wing

RCC work
RCC  completed till top slab

Flat finishing
Kitchen extension work completed from 4th to 19th floor.
Concealed plumbing completed from 4th to 19th floor, waterproofing is completed from 4th to 19th floor.

Common area finishing
Completed

Neo Valley – Sale building ( Kaveri )

construction not commenced yet

Neo Valley – Sale building ( Narmada )

construction not commenced yet

Neo Valley – Rehab building ( Sahjeevan )

RCC work

RCC work completed till top slab


Flat finishing

Internal & external finishing work completed 100%

165 flat possession handover

NeoPark – Rehab Building 

RCC work
Plinth RCC work 60% completed.

NeoPark – Sales building

RCC work
Piling work completed .

Tower Floor Details Detailed Updates
NeoSkies – Rehab building RCC work RCC work completed till 20th slab & 21st floor slab 5% completed
Finishing work Blockwork completed till 15th floor
Plumbing Conceal work completed upto 15th floor
Gypsum work completed upto 14th floor
Water proofing completed upto 11th floor
Flat flooring completed upto 4th floor
Infra STP pcc- 100% done, Raft r/f 100% completed , wall casting 60% completed , Top slab casting 20% completed.
NeoSkies – Sale building RCC work Plinth – 100% completed, 1st & 2nd Slab 100% completed, 3rd Slab completed till 30% .
NeoHills – Rehab building RCC work Pile , Excavation & Substructure work 100% completed , Superstructure 15th slab work in progress.
NeoHills – Sale building RCC work Substructure work 100% completed
Superstructure 1st floor slab in progress.
NeoSquare – A wing RCC work 2nd Slab completed
NeoSquare – B wing Ground to OHWT RCC completed
Flat Finishing Concealed plumbing completed Kitchen platform, flooring, gypsum, door installation completed (till 16th floor)
Common area finishing Gypsum on some of the floors completed
Services Only fire fighting completed
NeoSquare – C wing RCC RCC of main building completed
PAP unit – extension flat at 10th floor level
Chajja casting completed.
Flat finishing Kitchen extension work at 9th floor is in progress Rest finishing inside the flat is completed
Common area finishing Completed
Services Services of extra flat(PAP unit flat No 7) is pending rest is completed