% mentioned above is the current demand due as per the construction linked payment schedule
NeoSkies – Sale building
RCC work
Top RCC slab 100% completed.
Finishing work
Waterproofing work in progress ( 88% completed)
Conceal plumbing work in progress ( 94% completed)
Gypsum work 90% completed .
Flat flooring work 90% completed.
Door shutter work 88% completed.
Flat window work 60% completed.
NeoSkies – Rehab building
RCC work
OC received
Finishing work
177 flat possession handover
Infra
Sewage Treatment Plant & Plain Cement Concrete- 100% completed, Raft 100% completed , wall casting 100% completed , Top slab casting 100% completed.
NeoHills – Sale building
RCC work
23rd RCC slab completed
Finishing work
Waterproofing work in progress ( 85% completed)
Conceal plumbing work in progress ( 82% completed)
Gypsum work 45% completed .
Flat flooring work 81% completed.
Flat door shutter work 80% completed.
Flat window work 18% completed.
NeoHills – Rehab building
RCC work
Pile, Excavation ,Substructure & Superstructure work 100% completed
NeoSquare – A wing
RCC work
22nd slab casting completed & 23rd slab shuttering , reinforcement are work in progress.
Flat Finishing
Block work finalized till 18th floor & 19th floor work in progress.
Electric concealed work completed till 16th floor, 17th, 18th floor work in progress.
Gypsum plaster work completed till skirting level at 3rd, 5th to 15th floor ( excluding combined flats) 16th floor work in progress.
Waterproofing & plumbing work in progress at 3rd, 5th to 11th floor & base coat completed at 12th & 13th floor .
Tiling work & door frames work in progress.
Door frames making & fixing work in progress.
Main door frames fixing completed till 12th floor.
RCC Infra
UG water tank civil work in progress & rock anchoring is in progress for domestic & fire tank.
NeoSquare – B wing
RCC work completed till top slab.
Flat Finishing
Concealed plumbing completed
Hall extension civil work , Flooring , Gypsum plaster work completed from 9th to 19th .
Staircase flooring is completed from ground floor to till terrace.
Electric duct FRD door are fixed.
Schindler lift erection in progress.
NeoSquare – C wing
RCC work
RCC completed till top slab
Flat finishing
Kitchen extension work completed from 4th to 19th floor & 3rd floor work in progress.
Concealed plumbing completed from 4th to 19th floor, waterproofing is completed from 4th to 19th floor.
Electrical conducting work completed till 19th floor.
Terrace waterproofing work in progress.
Common area finishing
Completed
NeoValley ( Kaveri ) – Sale building
Excavation work started
NeoValley ( Kaveri ) – Rehab building ( Sahjeevan )
RCC work
RCC work completed till top slab
Flat finishing
Internal & external finishing work completed 100%
165 flat possession handover
NeoValley ( Narmada ) – Sale building
construction not commenced yet
NeoValley ( Narmada ) – Rehab building
Foundation work started
NeoPark – Rehab Building
RCC work
Plinth RCC work 100% completed.
1st slab work 50% completed.
NeoPark – Sales building
RCC work
Piling work completed .
Substructure work in progress
Part plinth work completed.
Tower | Floor Details | Detailed Updates |
---|---|---|
NeoSkies – Rehab building | RCC work | RCC work completed till 20th slab & 21st floor slab 5% completed |
Finishing work | Blockwork completed till 15th floor Plumbing Conceal work completed upto 15th floor Gypsum work completed upto 14th floor Water proofing completed upto 11th floor Flat flooring completed upto 4th floor |
|
Infra | STP pcc- 100% done, Raft r/f 100% completed , wall casting 60% completed , Top slab casting 20% completed. | |
NeoSkies – Sale building | RCC work | Plinth – 100% completed, 1st & 2nd Slab 100% completed, 3rd Slab completed till 30% . |
NeoHills – Rehab building | RCC work | Pile , Excavation & Substructure work 100% completed , Superstructure 15th slab work in progress. |
NeoHills – Sale building | RCC work | Substructure work 100% completed Superstructure 1st floor slab in progress. |
NeoSquare – A wing | RCC work | 2nd Slab completed |
NeoSquare – B wing | Ground to OHWT | RCC completed |
Flat Finishing | Concealed plumbing completed Kitchen platform, flooring, gypsum, door installation completed (till 16th floor) | |
Common area finishing | Gypsum on some of the floors completed | |
Services | Only fire fighting completed | |
NeoSquare – C wing | RCC | RCC of main building completed PAP unit – extension flat at 10th floor level Chajja casting completed. |
Flat finishing | Kitchen extension work at 9th floor is in progress Rest finishing inside the flat is completed | |
Common area finishing | Completed | |
Services | Services of extra flat(PAP unit flat No 7) is pending rest is completed |
Marathon Referral and Loyalty Program
Refer your friends to any Marathon property and get rewards worth 1% of your friend’s flat cost. Your friend gets a discount too. It’s a win-win.