Construction Updates, July 2022

Check updates:
NeoSkiesNeoHills
NeoSquareNeoValley

Update as on 6th July, 2022

NeoSkies
57%
NeoHills
39%
NeoSquare
33%
NeoValley
20%
NeoPark
20%

% mentioned above is the current demand due as per the construction linked payment schedule

NeoSkies – Sale building

RCC work
Plinth 100% completed, 13th slab 100% completed & 14th slab 20% completed

Finishing work
Waterproofing in progress till 4th floor .
Conceal plumbing in progress till 4th floor.
Excavation 100 % completed.

NeoSkies – Rehab building

RCC work
23rd slab completed 100%

Finishing work
Blockwork completed upto 20th floor
Plumbing work completed upto 20th floor
Gypsum work completed upto 20th floor
Waterproofing completed upto 20th floor
Flat flooring completed upto 19th floor
Electrical wiring done only on 10th floor
Lift installation in progress .
External painting in progress .

Infra
Sewage Treatment Plant &  Plain Cement Concrete- 100% completed, Raft 100% completed , wall casting 100% completed , Top slab casting 100% completed.

NeoHills – Sale building

RCC work
Substructure work 100% completed
Superstructure – 10th floor slab in progress.

NeoHills – Rehab building

RCC work
Pile, Excavation ,Substructure &  Superstructure work 100% completed

NeoSquare – A wing

RCC work
7th slab casting completed .

NeoSquare – B wing

RCC work completed till top slab .

Flat Finishing
Concealed plumbing completed
Hall extension civil work , Flooring , Gypsum plaster work completed from 9th to 19th .
Staircase flooring is completed till terrace.

NeoSquare – C wing

RCC
RCC  completed till top slab

Flat finishing
Kitchen extension work completed till 19th floor.
Concealed plumbing completed till 14th floor, waterproofing is completed till 10th floor. Kitchen platform & flooring work in progress.

Common area finishing
Completed

NeoValley

Construction not commenced yet

NeoPark

Construction not commenced yet

Tower Floor Details Detailed Updates
NeoSkies – Rehab building RCC work RCC work completed till 20th slab & 21st floor slab 5% completed
Finishing work Blockwork completed till 15th floor
Plumbing Conceal work completed upto 15th floor
Gypsum work completed upto 14th floor
Water proofing completed upto 11th floor
Flat flooring completed upto 4th floor
Infra STP pcc- 100% done, Raft r/f 100% completed , wall casting 60% completed , Top slab casting 20% completed.
NeoSkies – Sale building RCC work Plinth – 100% completed, 1st & 2nd Slab 100% completed, 3rd Slab completed till 30% .
NeoHills – Rehab building RCC work Pile , Excavation & Substructure work 100% completed , Superstructure 15th slab work in progress.
NeoHills – Sale building RCC work Substructure work 100% completed
Superstructure 1st floor slab in progress.
NeoSquare – A wing RCC work 2nd Slab completed
NeoSquare – B wing Ground to OHWT RCC completed
Flat Finishing Concealed plumbing completed Kitchen platform, flooring, gypsum, door installation completed (till 16th floor)
Common area finishing Gypsum on some of the floors completed
Services Only fire fighting completed
NeoSquare – C wing RCC RCC of main building completed
PAP unit – extension flat at 10th floor level
Chajja casting completed.
Flat finishing Kitchen extension work at 9th floor is in progress Rest finishing inside the flat is completed
Common area finishing Completed
Services Services of extra flat(PAP unit flat No 7) is pending rest is completed

Marathon Referral and Loyalty Program

Refer your friends to any Marathon property and get rewards worth 1% of your friend’s flat cost. Your friend gets a discount too. It’s a win-win.