Construction Updates, July 2023

Check updates:
NeoSkiesNeoHills
NeoSquareNeoValley • NeoPark

Update as on 5th July, 2023

NeoSkies
73%
NeoHills
75%
NeoSquare
57%
NeoValley, Kaveri
20%
NeoValley, Narmada
10%
NeoPark
20%

% mentioned above is the current demand due as per the construction linked payment schedule

NeoSkies – Sale building

RCC work
Top RCC slab 100% completed.

Finishing work
Waterproofing work in progress ( 77% completed)
Conceal plumbing work in progress ( 91% completed)
Gypsum work 89% completed .
Flat flooring work 74% completed.
Door shutter work in progress.

NeoSkies – Rehab building

RCC work
OC received

Finishing work
177 flat possession handover

Infra
Sewage Treatment Plant &  Plain Cement Concrete- 100% completed, Raft 100% completed , wall casting 100% completed , Top slab casting 100% completed.

NeoHills – Sale building

RCC work
23rd RCC slab completed

NeoHills – Rehab building

RCC work
Pile, Excavation ,Substructure &  Superstructure work 100% completed

NeoSquare – A wing

RCC work
18th slab casting completed & 19th part 1st casting completed & 2nd part casting work in progress.

Flat Finishing
Block work finalized till 8th floor & 9th floor work in progress.
Electric concealed work completed till 14th floor, 15th floor work in progress.
Gypsum plaster work completed till 9th floor.
Waterproofing & plumbing work in progress at 10th floor.
Tiling work & door frames work in progress.
Door frames making & fixing work in progress.

RCC Infra
UG water tank civil work in progress & rock anchoring is in progress for domestic & fire tank.

NeoSquare – B wing

RCC work completed till top slab.

Flat Finishing
Concealed plumbing completed
Hall extension civil work , Flooring , Gypsum plaster work completed from 9th to 19th .
Staircase flooring is completed from ground floor to till terrace.
Electric duct FRD door are fixed.
Schindler lift erection in progress.

NeoSquare – C wing

RCC work
RCC  completed till top slab

Flat finishing
Kitchen extension work completed from 4th to 19th floor.
Concealed plumbing completed from 4th to 19th floor, waterproofing is completed from 4th to 19th floor.
Electrical conducting work completed till 19th floor.
Terrace waterproofing work in progress.

Common area finishing
Completed

NeoValley  ( Kaveri ) – Sale building 

Excavation work started

NeoValley ( Kaveri ) – Rehab building ( Sahjeevan )

RCC work
RCC work completed till top slab

Flat finishing
Internal & external finishing work completed 100%
165 flat possession handover

NeoValley  ( Narmada ) – Sale building 

construction not commenced yet

NeoValley  ( Narmada ) – Rehab building 

construction not commenced yet

NeoPark – Rehab Building 

RCC work
Plinth RCC work 90% completed.

NeoPark – Sales building

RCC work
Piling work completed .
Foundation work in progress.

Tower Floor Details Detailed Updates
NeoSkies – Rehab building RCC work RCC work completed till 20th slab & 21st floor slab 5% completed
Finishing work Blockwork completed till 15th floor
Plumbing Conceal work completed upto 15th floor
Gypsum work completed upto 14th floor
Water proofing completed upto 11th floor
Flat flooring completed upto 4th floor
Infra STP pcc- 100% done, Raft r/f 100% completed , wall casting 60% completed , Top slab casting 20% completed.
NeoSkies – Sale building RCC work Plinth – 100% completed, 1st & 2nd Slab 100% completed, 3rd Slab completed till 30% .
NeoHills – Rehab building RCC work Pile , Excavation & Substructure work 100% completed , Superstructure 15th slab work in progress.
NeoHills – Sale building RCC work Substructure work 100% completed
Superstructure 1st floor slab in progress.
NeoSquare – A wing RCC work 2nd Slab completed
NeoSquare – B wing Ground to OHWT RCC completed
Flat Finishing Concealed plumbing completed Kitchen platform, flooring, gypsum, door installation completed (till 16th floor)
Common area finishing Gypsum on some of the floors completed
Services Only fire fighting completed
NeoSquare – C wing RCC RCC of main building completed
PAP unit – extension flat at 10th floor level
Chajja casting completed.
Flat finishing Kitchen extension work at 9th floor is in progress Rest finishing inside the flat is completed
Common area finishing Completed
Services Services of extra flat(PAP unit flat No 7) is pending rest is completed

Marathon Referral and Loyalty Program

Refer your friends to any Marathon property and get rewards worth 1% of your friend’s flat cost. Your friend gets a discount too. It’s a win-win.