Construction Updates, June 2021
Construction Updates, June 2021
NeoSkies
NeoHills
NeoSquare
NeoValley
% mentioned above is the current demand due as per the construction linked payment schedule
Tower | Floor Details | Detailed Updates |
---|---|---|
NeoSkies – Rehab building | RCC work | RCC work of 13th floor is in progress – 50% done |
Finishing work | Blockwork completed till 10th floor starting from 4th floor Plumbing Conceal work completed upto 8th floor starting from 4th floor Gypsum work ip on 4th floor -80% completed Water proofing ip on 4th floor – 50% completed Electrical Conceal Work in block work completed upto 8th floor starting from 4th floor Door Frame fixing work completed only on sample floor Window rough ground marble fixing completed only on sample floor Window sill fixing completed only on sample floor Tiling & dado completed only on sample floor Kitchen Platform fixing completed only on sample floor |
|
Infra | STP excavation ip – 70% done | |
NeoSkies – Sale building | RCC work | RCC work of 1st floor slab ip |
NeoHills – Rehab building | RCC work | RCC work of 2nd floor slab in progress |
NeoHills – Sale building | RCC work | Substructure work in progress including piling work- 70% done |
NeoSquare – A wing | RCC work | Plinth completed, 1st slab work is in process |
NeoSquare – B wing | Ground to OHWT | RCC completed |
Flat Finishing | Concealed plumbing completed Kitchen platform, flooring, gypsum, door installation completed |
|
Common area finishing | Pending | |
Services | Only fire fighting completed | |
NeoSquare – C wing | RCC | RCC of main building completed PAP unit – extension flat at 4th floor level Chajja casting for kitchen completed from Gr to 12th floor |
Flat finishing | Kitchen extension work at 4th floor is in progress, rest work is completed | |
Common area finishing | Completed | |
Services | Services of extra flat flat is pending rest is completed |