% mentioned above is the current demand due as per the construction linked payment schedule
NeoSkies – Sale building
RCC work
Plinth – 100% completed, 12th slab 100% completed & 13th slab 50% completed
Finishing work
Waterproofing in progress on 4th floor .
Conceal plumbing in progress on 4th floor.
Excavation in progress 40% completed.
NeoSkies – Rehab building
RCC work
23rd slab completed 100%
Finishing work
Blockwork completed till 20th floor
Plumbing work completed upto 20th floor
Gypsum work completed upto 20th floor
Waterproofing completed upto 20th floor
Flat flooring completed upto 19th floor
Electrical wiring done only on 10th floor
Lift installation in progress 20% completed
Firefighting flats completed upto 18th floor
External painting in progress 25% completed.
Infra
STP PCC – 100% done, Raft 100% completed , wall casting 100% completed , Top slab casting 100% completed.
NeoHills – Sale building
RCC work
Substructure work 100% completed
Superstructure – 8th floor slab in progress.
NeoHills – Rehab building
RCC work
Pile, Excavation & Substructure work 100% completed
Superstructure – OHWT work in progress.
NeoSquare – A wing
RCC work
6th slab casting completed , 7th slab shuttering & reinforcement completed
NeoSquare – B wing
RCC completed till top slab
Flat Finishing
Concealed plumbing completed
Hall extension civil work , flooring completed from 19th to 9th , Gypsum plaster work in progress from 9th To 19th floor .
Grinding is completed and repairing work in progress.
Staircase flooring is completed from 3rd to 14th floor .
NeoSquare – C wing
RCC
RCC of main building completed till top slab
RCC of 7th floor extension flat 17th slab casted, Shuttering & reinforcement of 18th slab is completed.
Flat finishing
Kitchen extension work completed in 63 flats.
Rest finishing inside the flat is completed
Concealed plumbing completed from 4th To 10th floor , waterproofing is completed from 4th to 10th floor.
Common area finishing
Completed
NeoValley
Construction not commenced yet
Tower | Floor Details | Detailed Updates |
---|---|---|
NeoSkies – Rehab building | RCC work | RCC work completed till 20th slab & 21st floor slab 5% completed |
Finishing work | Blockwork completed till 15th floor Plumbing Conceal work completed upto 15th floor Gypsum work completed upto 14th floor Water proofing completed upto 11th floor Flat flooring completed upto 4th floor |
|
Infra | STP pcc- 100% done, Raft r/f 100% completed , wall casting 60% completed , Top slab casting 20% completed. | |
NeoSkies – Sale building | RCC work | Plinth – 100% completed, 1st & 2nd Slab 100% completed, 3rd Slab completed till 30% . |
NeoHills – Rehab building | RCC work | Pile , Excavation & Substructure work 100% completed , Superstructure 15th slab work in progress. |
NeoHills – Sale building | RCC work | Substructure work 100% completed Superstructure 1st floor slab in progress. |
NeoSquare – A wing | RCC work | 2nd Slab completed |
NeoSquare – B wing | Ground to OHWT | RCC completed |
Flat Finishing | Concealed plumbing completed Kitchen platform, flooring, gypsum, door installation completed (till 16th floor) | |
Common area finishing | Gypsum on some of the floors completed | |
Services | Only fire fighting completed | |
NeoSquare – C wing | RCC | RCC of main building completed PAP unit – extension flat at 10th floor level Chajja casting completed. |
Flat finishing | Kitchen extension work at 9th floor is in progress Rest finishing inside the flat is completed | |
Common area finishing | Completed | |
Services | Services of extra flat(PAP unit flat No 7) is pending rest is completed |