CONSTRUCTION UPDATES

MARCH 2021

CONSTRUCTION UPDATES

MARCH 2021

NeoSkies
26%
NeoHills
15%
NeoSquare
15%
NeoValley
9%
Tower Updates
NeoSkies Possession June 2023
Plinth slab completed
Ground Floor lobby slab in progress
Grade slab in progress
NeoHills Possession June 2023
Substructure (footing) work going on
Rehab Tower – 2nd slab
NeoSquare Construction to commence soon
NeoValley Construction to commence soon