Construction Updates, March 2022

Check updates:
NeoSkiesNeoHills
NeoSquareNeoValley

Update as on 4th March, 2022

NeoSkies
42%
NeoHills
21%
NeoSquare
27%
NeoValley
20%

% mentioned above is the current demand due as per the construction linked payment schedule

NeoSkies – Sale building

RCC work
Plinth – 100% completed, 8th slab 100% completed & 9th slab 15% completed

NeoSkies – Rehab building

RCC work
23rd slab completed 50%

Finishing work
Blockwork completed till 18th floor
Plumbing work completed upto 19th floor
Gypsum work completed upto 17th floor
Waterproofing completed upto 18th floor
Flat flooring completed upto 14th floor

Infra
STP PCC – 100% done, Raft 100% completed , wall casting 90% completed , Top slab casting 100% completed.

NeoHills – Sale building

RCC work
Substructure work 100% completed
Superstructure – 3rd floor slab in progress.

NeoHills – Rehab building

RCC work
Pile, Excavation & Substructure work 100% completed
Superstructure – 22nd slab work in progress.

NeoSquare – A wing

RCC work
4th slab casting completed , 5th slab shuttering & reinforcement completed

NeoSquare – B wing

RCC completed till top slab

Flat Finishing
Concealed plumbing completed
Kitchen platform, flooring, gypsum, door installation completed till 16th floor

NeoSquare – C wing

RCC
RCC of main building completed till top slab
RCC of 7th floor extension flat 13th slab casted

Flat finishing
Kitchen extension work at 11th floor is in progress
Rest finishing inside the flat is completed

Common area finishing
Completed

NeoValley

Construction not commenced yet

Tower Floor Details Detailed Updates
NeoSkies – Rehab building RCC work RCC work completed till 20th slab & 21st floor slab 5% completed
Finishing work Blockwork completed till 15th floor
Plumbing Conceal work completed upto 15th floor
Gypsum work completed upto 14th floor
Water proofing completed upto 11th floor
Flat flooring completed upto 4th floor
Infra STP pcc- 100% done, Raft r/f 100% completed , wall casting 60% completed , Top slab casting 20% completed.
NeoSkies – Sale building RCC work Plinth – 100% completed, 1st & 2nd Slab 100% completed, 3rd Slab completed till 30% .
NeoHills – Rehab building RCC work Pile , Excavation & Substructure work 100% completed , Superstructure 15th slab work in progress.
NeoHills – Sale building RCC work Substructure work 100% completed
Superstructure 1st floor slab in progress.
NeoSquare – A wing RCC work 2nd Slab completed
NeoSquare – B wing Ground to OHWT RCC completed
Flat Finishing Concealed plumbing completed Kitchen platform, flooring, gypsum, door installation completed (till 16th floor)
Common area finishing Gypsum on some of the floors completed
Services Only fire fighting completed
NeoSquare – C wing RCC RCC of main building completed
PAP unit – extension flat at 10th floor level
Chajja casting completed.
Flat finishing Kitchen extension work at 9th floor is in progress Rest finishing inside the flat is completed
Common area finishing Completed
Services Services of extra flat(PAP unit flat No 7) is pending rest is completed