% mentioned above is the current demand due as per the construction linked payment schedule
NeoSkies – Sale building
RCC work
Plinth 100% completed, 21st RCC slab 100% completed.
Finishing work
Waterproofing in progress up to 20th floor (50% completed)
Conceal plumbing in progress up to 18th floor ( 50% completed)
Gypsum work completed up to 19th floor.
Flat flooring completed up to 16th floor.
Door shutter work completed till 10th floor.
NeoSkies – Rehab building
RCC work
23rd RCC slab completed.
Finishing work
Block work completed up to 22nd floor
Plumbing work completed up to 22nd floor
Gypsum work completed up to 21st floor
Waterproofing completed up to 22nd floor
Lobby flooring completed up to 22nd floor.
Flat flooring completed up to 22nd floor.
Electrical wiring done only on 20th floor.
Fire fighting flats completed up to 22nd floor.
Lift installation in progress 95% completed.
External painting in progress 95% completed.
Infra
Sewage Treatment Plant & Plain Cement Concrete- 100% completed, Raft 100% completed , wall casting 100% completed , Top slab casting 100% completed.
NeoHills – Sale building
RCC work
Substructure work 100% completed
Superstructure – 22nd slab completed & 23rd floor slab in progress.
NeoHills – Rehab building
RCC work
Pile, Excavation ,Substructure & Superstructure work 100% completed
NeoSquare – A wing
RCC work
14th slab casting completed & 15th slab shuttering & reinforcement work in progress.
Flat Finishing
Block work finalized till 8th floor & 9th floor work in progress.
Gypsum plaster & electric concealed conducting work in process on 7th floor.
Waterproofing & plumbing work in progress at 8th floor.
Tiling work & door frames work in progress.
NeoSquare – B wing
RCC work completed till top slab .
Flat Finishing
Concealed plumbing completed
Hall extension civil work , Flooring , Gypsum plaster work completed from 9th to 19th .
Staircase flooring is completed from ground floor to till terrace.
NeoSquare – C wing
RCC work
RCC completed till top slab
Flat finishing
Kitchen extension work completed from 4th to 19th floor.
Concealed plumbing completed from 4th to 19th floor, waterproofing is completed from 4th to 19th floor.
Common area finishing
Completed
Neo Valley – Sale building
construction not commenced yet
Neo Valley – Rehab building
RCC work
RCC work completed till top slab
Flat finishing
Internal & external finishing work completed 100%
165 flat possession handover
NeoPark – Rehab Building
RCC work
Plinth RCC work 60% completed.
NeoPark – Sales building
RCC work
Piling work completed .
Tower | Floor Details | Detailed Updates |
---|---|---|
NeoSkies – Rehab building | RCC work | RCC work completed till 20th slab & 21st floor slab 5% completed |
Finishing work | Blockwork completed till 15th floor Plumbing Conceal work completed upto 15th floor Gypsum work completed upto 14th floor Water proofing completed upto 11th floor Flat flooring completed upto 4th floor |
|
Infra | STP pcc- 100% done, Raft r/f 100% completed , wall casting 60% completed , Top slab casting 20% completed. | |
NeoSkies – Sale building | RCC work | Plinth – 100% completed, 1st & 2nd Slab 100% completed, 3rd Slab completed till 30% . |
NeoHills – Rehab building | RCC work | Pile , Excavation & Substructure work 100% completed , Superstructure 15th slab work in progress. |
NeoHills – Sale building | RCC work | Substructure work 100% completed Superstructure 1st floor slab in progress. |
NeoSquare – A wing | RCC work | 2nd Slab completed |
NeoSquare – B wing | Ground to OHWT | RCC completed |
Flat Finishing | Concealed plumbing completed Kitchen platform, flooring, gypsum, door installation completed (till 16th floor) | |
Common area finishing | Gypsum on some of the floors completed | |
Services | Only fire fighting completed | |
NeoSquare – C wing | RCC | RCC of main building completed PAP unit – extension flat at 10th floor level Chajja casting completed. |
Flat finishing | Kitchen extension work at 9th floor is in progress Rest finishing inside the flat is completed | |
Common area finishing | Completed | |
Services | Services of extra flat(PAP unit flat No 7) is pending rest is completed |