Construction Updates, September 2021
Construction Updates, September 2021
NeoSkies
NeoHills
NeoSquare
NeoValley
% mentioned above is the current demand due as per the construction linked payment schedule
Tower | Floor Details | Detailed Updates |
---|---|---|
NeoSkies – Rehab building | RCC work | RCC work completed till 16th slab 95% |
Finishing work | Blockwork completed till 12th floor Plumbing Conceal work completed upto 8th floor starting from 4th floor Gypsum work completed upto 8th floor Water proofing completed upto 8th floor Electrical Conceal Work in block work completed upto 9th floor |
|
Infra | STP pcc- 80% done, Raft r/f 60% completed | |
NeoSkies – Sale building | RCC work | Plinth – 100% completed, ground floor work ip – 95 % completed |
NeoHills – Rehab building | RCC work | RCC work of 7th floor slab in progress |
NeoHills – Sale building | RCC work | Substructure work till 107.5m level complete 1st plinth level completed, 110.4m 2nd plinth level slab in progress |
NeoSquare – A wing | RCC work | 1st slab casting completed ,2nd slab column casting till beam bottom level completed |
NeoSquare – B wing | Ground to OHWT | RCC completed |
Flat Finishing | Concealed plumbing completed Kitchen platform, flooring, gypsum, door installation completed (till 16th floor) | |
Common area finishing | Gypsum on some of the floors completed | |
Services | Only fire fighting completed | |
NeoSquare – C wing | RCC | RCC of main building completed PAP unit – extension flat at 8th floor level Chajja casting for kitchen completed from Gr to 12th floor |
Flat finishing | Kitchen extension work at 8th floor is in progress Rest finishing inside the flat is completed | |
Common area finishing | Completed | |
Services | Services of extra flat(PAP unit flat No 7) is pending rest is completed |