Construction Updates, June 2021

Construction Updates, June 2021

Coral
79%
Sapphire
36%

% mentioned above is the current demand due as per the construction linked payment schedule.

Tower Name Detailed Updates

Opal

OC Received

Topaz

OC Received

Amber

OC Received

Emerald

OC Received

Coral

RCC work upto OHWT bottom slab completed
Water tank wall in progress- 10% completed
Blockwork completed till 16th  floor
Plumbing Conceal work completed upto 15th Floor
Gypsum work completed upto 15th Floor
Water proofing completed upto 13th Floor
Electrical Conceal Work in block work completed upto 15th Floor
Firefighting pipe installation in lobby and flats completed upto 13th floor
External painting in progress- 75% completed
Window rough ground marble fixing completed upto 10th Floor
Toilet flooring and dado completed upto 10th floor
Kitchen Platform fixing completed upto 10th Floor

Sapphire

RCC work – 1st slab completed
Mivan setting at 1st floor in progress

Emerald

Possession Date: Dec 2022
OC Received

Sapphire

Possession Date: Dec 2022
RERA No.: P51700001265

Coral

Possession Date: Dec 2022
RERA No.: P51700000952