Construction Updates, December 2021

Update as on 6th December, 2021

Construction Updates, December 2021

Update as on 6th December, 2021

Sapphire
40%
Coral
85%

% mentioned above is the current demand due as per the construction linked payment schedule.

Tower Name Detailed Updates

Opal

OC Received

Topaz

OC Received

Amber

OC Received

Emerald

OC Received

Coral

Completed RCC work upto Over Head Water Tank (OWHT)
RCC work upto OHWT top slab casting completed
Blockwork completed till 16th floor.
Plumbing work completed upto 16th Floor
Gypsum work completed upto 16th Floor
Water proofing completed upto 16th Floor
Electrical work completed till 16th floor
Firefighting pipe installation in lobby and flats completed upto 15th floor
External painting in progress – 90% completed
Window, marble fixing completed upto 15th Floor
Toilet flooring and dado completed upto 16th floor
Kitchen Platform fixing and dado completed upto 16th Floor
Flat Flooring completed upto 14th floor
Typical lobby flooring completed upto 15th floor
Internal lift of building 3 nos completed

Sapphire

RCC work – 3rd Slab completed , 4th slab in progress .

Emerald

Possession Date: Dec 2022
OC Received

Sapphire

Possession Date: Jun 2023
RERA No.: P51700001265

Coral

Possession Date: Jun 2023
RERA No.: P51700000952