Construction Updates, February 2022

Update as on 3rd February, 2022

Construction Updates, February 2022

Update as on 3rd February, 2022

Sapphire
42%
Coral
87%

% mentioned above is the current demand due as per the construction linked payment schedule.

Tower Name Detailed Updates

Opal

OC Received

Topaz

OC Received

Amber

OC Received

Emerald

OC Received

Coral

Completed RCC work upto Over Head Water Tank (OWHT)
RCC work upto OHWT top slab casting completed
Blockwork completed till 16th floor.
Plumbing work completed upto 16th Floor
Gypsum work completed upto 16th Floor
Water proofing completed upto 16th Floor , 3rd & 15th floor balance.Terrace slab entire waterproofing completed.Over head water tank waterproofing in progress.
Electrical Conceal Work in block work completed till 16th floor.(1st floor balance only 3 sample flats 101,111,112 completed)
Firefighting pipe installation in lobby and flats completed upto 16th floor
External painting in progress – 90% completed
Window, marble fixing completed upto 15th Floor
Toilet flooring and dado completed upto 16th floor, Only 1st floor in progress.
Kitchen Platform fixing and dado completed upto 16th Floor only 1st floor in progress.
Flat Flooring completed upto 16th floor only 1st floor is balance.
Typical lobby flooring  & Dado completed upto 16th floor only  5th floor is balance.
2 nos of staircase railing & grill completed from 1st to 16th floor.
GI FRD door in lobby area for Fire & Electrical shaft completed upto 16th floor, Maer rooms, pannel room completed
Internal lift of building 3 nos completed

Sapphire

RCC work – 5th Slab completed

Emerald

Possession Date: Dec 2022
OC Received

Sapphire

Possession Date: Jun 2023
RERA No.: P51700001265

Coral

Possession Date: Jun 2023
RERA No.: P51700000952