Construction Updates, June 2022

Update as on 5th June, 2022

Construction Updates, June 2022

Update as on 5th June, 2022

Sapphire
54%
Coral
90%

% mentioned above is the current demand due as per the construction linked payment schedule.

Tower Name Detailed Updates

Opal

OC Received

Topaz

OC Received

Amber

OC Received

Emerald

OC Received

Coral

Completed RCC work upto Over Head Water Tank (OWHT)
RCC work upto OHWT top slab casting completed
Blockwork completed till 16th floor.
Plumbing Conceal work completed upto 16th Floor.Only 15th floor is balance. Plumbing work in 12 nos of shaft completed. Terrace looping 95% completed.
Gypsum work completed upto 16th Floor in lobby area and flat punning also completed upto 16th floor, jad finish in flats in progress at 12th floor.
Water proofing completed upto 16th Floor, 3rd and 15th floor is balance. Terrace slab entire waterproofing completed. Over Head water tank waterproofing completed. UGWT waterproofing completed. 5 nos of shops waterproofing in progress- 65% completed.
Electrical Conceal Work in block work completed till 16th floor.(1st floor balance only 3 sample flats 101,111,112 completed). Electrical wiring from meter room to shaft completed also staircase, lobby and refuge area wiring completed. Internal flat wiring in progress- 65 % completed.
Entire fire fighting work in building completed.
External painting in progress – 95% completed
Window, marble fixing completed upto 16th Floor
Toilet flooring and dado completed upto 16th floor.
Kitchen Platform fixing and dado completed upto 16th Floor
Flat Flooring completed upto 16th floor .
Lift achitrave of 3 nos of lift completed from 1st to 16th floor.
Installation of window completed upto 16th floor.
Typical lobby flooring  & Dado completed upto 16th floor.
2 nos of staircase railing & grill completed from 1st to 16th floor.
Installation of window complete upto 16th floor.
2 nos of staircase wooden FRD door installation completed.
Main door shutter of flats installation from 1st to 16th floor completed.
Infra- RWH line, Fire line, Drainage line, water supply line, Road work in progress – 95 % completed, paver fixing work in progress 75 % completed.
Coral substation in progress 70% completed.
GI FRD door in lobby area for Fire & Electrical shaft completed upto 16th floor, meter rooms , Panel room completed.
Internal lift of building 3 nos completed

Sapphire

RCC work- 7th slab complted, 8th slab in progress 35% completed.

Emerald

Possession Date: Dec 2022
OC Received

Sapphire

Possession Date: Jun 2023
RERA No.: P51700001265

Coral

Possession Date: Jun 2023
RERA No.: P51700000952