Construction Updates, July 2022

Update as on 6th July, 2022

Construction Updates, July 2022

Update as on 6th July, 2022

Sapphire
54%
Coral
90%

% mentioned above is the current demand due as per the construction linked payment schedule.

Tower Name Detailed Updates

Opal

OC Received

Topaz

OC Received

Amber

OC Received

Emerald

OC Received

Coral

Completed RCC work upto Over Head Water Tank (OWHT)
Blockwork completed till 16th floor.
Plumbing Conceal work completed .
Gypsum work completed upto 16th Floor .
Water proofing completed upto terrace slab .
Electrical Conceal Work in block work completed till 16th floor.
Fire fighting work completed.
External painting completed 95 % .
Window, marble fixing completed upto 16th Floor.
Toilet flooring completed upto 16th Floor.
Kitchen Platform fixing upto 16th Floor.
Flat Flooring completed upto 16th floor .
Lift architrave of 3 nos of lift completed till 16th Floor.
Installation of window completed upto 16th floor.
Infra work in progress.
Coral substation completed 75% .

Sapphire

RCC work- 7th slab completed, 8th slab in progress 35% completed.

Emerald

Possession Date: Dec 2022
OC Received

Sapphire

Possession Date: Jun 2023
RERA No.: P51700001265

Coral

Possession Date: Jun 2023
RERA No.: P51700000952