Construction Updates, September 2022

Update as on 8th September, 2022

Construction Updates, September 2022

Update as on 8th September, 2022

Sapphire
54%
Coral
92%
Ruby
10%

% mentioned above is the current demand due as per the construction linked payment schedule.

Tower Name Detailed Updates

Opal

OC Received

Topaz

OC Received

Amber

OC Received

Emerald

OC Received

Coral

RCC work completed.
Plumbing Conceal work completed .
Gypsum & water proofing work completed up to 16th Floor .
Water proofing completed up to 16th floor.
Electrical Conceal Work completed till 16th floor.
Fire fighting work completed.
External painting completed 95 % .
Window, marble fixing completed up to 16th Floor.
Kitchen Platform , flat flooring completed up to 16th Floor.
Lift architrave of 3 nos of lift completed till 16th Floor.
Infra work in progress.
Coral substation completed 75% .

Sapphire

8th slab RCC completed, 9th slab RCC work in progress 50% completed.
Gypsum work in progress at 1st floor.

Ruby

Excavation Work Started 

Amenities  Updates

Club House

Plinth beam work 25% completed

Emerald

Possession Date: Dec 2022
OC Received

Sapphire

Possession Date: Jun 2023
RERA No.: P51700001265

Coral

Possession Date: Jun 2023
RERA No.: P51700000952

Ruby

Possession Date: Dec 2026
RERA No.: P51700021189