Construction Updates,May 2023

Update as on 4th May, 2023

Construction Updates,May 2023

Update as on 4th May, 2023

Sapphire
67%
Ruby
40%

% mentioned above is the current demand due as per the construction linked payment schedule.

Tower Name Detailed Updates

Opal

OC Received

Topaz

OC Received

Amber

OC Received

Emerald

OC Received

Coral

OC Received 

Sapphire

15th slab RCC completed.
16th RCC slab in progress.
Gypsum plaster work completed till 10th floor & 11th floor work in progress.
Block work completed up to 9th floor & 10th floor work in progress.
Conceal plumbing work on wall 1st to 7th floor completed.
Toilet internal drainage work in progress.
Kitchen platform work in progress.
Internal water proofing 1st floor completed & 2nd floor in progress.
Internal fire fighting work in progress

Ruby

Excavation 100% completed.
Footing work , Stub column & plinth beam 100% completed & back filling 100% completed. Grid slab 100% completed.
Stilt floor column work in progress.

Amenities  Updates

Club House

Plinth beam work 100% completed,Back filling 100% completed & Stilt level PCC 100% completed.

Sub structure work completed.
Plinth beam completed.
Multipurpose court 100% completed.

Emerald

Possession Date: Dec 2022
OC Received

Sapphire

Possession Date: Jun 2023
RERA No.: P51700001265

Coral

Possession Date: Jun 2023
RERA No.: P51700000952

Ruby

Possession Date: Dec 2026
RERA No.: P51700021189