Construction Updates, December 2022

Update as on 3rd December, 2022

Construction Updates,December 2022

Update as on 3rd December, 2022

Sapphire
64%
Ruby
25%

% mentioned above is the current demand due as per the construction linked payment schedule.

Tower Name Detailed Updates

Opal

OC Received

Topaz

OC Received

Amber

OC Received

Emerald

OC Received

Coral

OC Received 

Sapphire

11th slab RCC completed.
12th RCC slab 70% completed
Gypsum punning work in progress till 5th floor & 6th floor in progress.

Ruby

Excavation 80% completed.

Amenities  Updates

Club House

Plinth beam work 100% completed,Back filling 100% completed & Stilt level PCC in progress

Emerald

Possession Date: Dec 2022
OC Received

Sapphire

Possession Date: Jun 2023
RERA No.: P51700001265

Coral

Possession Date: Jun 2023
RERA No.: P51700000952

Ruby

Possession Date: Dec 2026
RERA No.: P51700021189