Construction Updates, July 2022
Update as on 6th July, 2022
Construction Updates, July 2022
Update as on 6th July, 2022
% mentioned above is the current demand due as per the construction linked payment schedule.
Tower Name | Detailed Updates |
---|---|
Opal |
OC Received |
Topaz |
OC Received |
Amber |
OC Received |
Emerald |
OC Received |
Coral |
Completed RCC work upto Over Head Water Tank (OWHT) |
Sapphire |
RCC work- 7th slab completed, 8th slab in progress 35% completed. |
Emerald
Possession Date: Dec 2022
OC Received
Sapphire
Possession Date: Jun 2023
RERA No.: P51700001265
Coral
Possession Date: Jun 2023
RERA No.: P51700000952