Construction Updates,March 2023

Update as on 2nd March, 2023

Construction Updates,March 2023

Update as on 2nd March, 2023

Sapphire
67%
Ruby
25%

% mentioned above is the current demand due as per the construction linked payment schedule.

Tower Name Detailed Updates

Opal

OC Received

Topaz

OC Received

Amber

OC Received

Emerald

OC Received

Coral

OC Received 

Sapphire

14th slab RCC completed.
15th RCC slab in progress.
Gypsum punning work completed till 9th floor.
Block work completed up to 7th floor & 8th floor work in progress.
Conceal plumbing work on wall 1st to 7th floor completed.
Toilet internal drainage work in progress.
Internal water proofing 1st floor completed & 2nd floor in progress.

Ruby

Excavation 100% completed.
Footing work , Stub column & plinth beam 100% completed & back filling 100% completed. Grid slab 100% completed..

Amenities  Updates

Club House

Plinth beam work 100% completed,Back filling 100% completed & Stilt level PCC 100% completed.

Superstructure 1st floor column 75% completed.

Emerald

Possession Date: Dec 2022
OC Received

Sapphire

Possession Date: Jun 2023
RERA No.: P51700001265

Coral

Possession Date: Jun 2023
RERA No.: P51700000952

Ruby

Possession Date: Dec 2026
RERA No.: P51700021189