Construction Updates, November 2021

Construction Updates, November 2021

Coral
85%
Sapphire
36%

% mentioned above is the current demand due as per the construction linked payment schedule.

Tower Name Detailed Updates

Opal

OC Received

Topaz

OC Received

Amber

OC Received

Emerald

OC Received

Coral

Completed RCC work upo Over Head Water Tank
RCC work upto OHWT top slab casting completed
Blockwork completed till 16th floor.
Plumbing Conceal work completed upto 16th Floor. 15th floor is balance
Gypsum work completed upto 16th Floor,1st floor balance
Water proofing completed upto 16th Floor, 1st and 15th floor is balance
Electrical Conceal Work in block work completed till 16th floor.(1st floor balance only 3 sample flats 101,111,112 completed)
Firefighting pipe installation in lobby and flats completed upto 15th floor
External painting in progress- 90% completed
Window rough ground marble fixing completed upto 15th Floor
Toilet flooring and dado completed upto 14th floor
Kitchen Platform fixing and dado completed upto 12th Floor
Flat Flooring completed upto 10th floor (only marathon flats)
Typical lobby flooring completed upto 10th floor

Sapphire

RCC work – 2nd slab completed, 3rd slab is in progress

Emerald

Possession Date: Dec 2022
OC Received

Sapphire

Possession Date: Dec 2022
RERA No.: P51700001265

Coral

Possession Date: Dec 2022
RERA No.: P51700000952