Construction Updates – March 2021

Construction Updates – March 2021

AURA
ELARA
Tower Updates
Aura Detailed updates (Possession – July 2022):
Completed RCC work upto 21st floor, 22nd floor RCC work in progress (80 % Completed).
Blockwork completed till 21st floor.
Plumbing Conceal work completed upto 21st Floor.
Gypsum work completed upto 21st Floor.
Water proofing completed upto 21st Floor.
Electrical Conceal Work in block work completed upto 21st Floor.
Door Frame fixing work completed upto 4th Floor.
Window rough ground marble fixing completed upto 21st Floor.
Window sill fixing completed upto 21st floor.
Tiling & dado completed in 158 Flats. Partly completed till 21st floor as per listed flats.
Kitchen Platform fixing completed in 158 Flats. Partly completed till 21st floor as per listed flats.
Elara RCC work upto 21st floor completed.
RCC work of 22nd floor is in progress.
Blockwork completed till 7th floor.
Plumbing Conceal work completed upto 2nd Floor
Gypsum work in progress on 1st Floor.
Water proofing in progress on 1st Floor.