Construction Updates – December 2021

Update as on 3rd December, 2021

Construction Updates – December 2021

Update as on 3rd December, 2021

AURA - 1
AURA - 2
AURA - 3
ELARA - 1
ELARA - 2
Tower Updates
Aura Detailed updates (Possession – Dec 2022):
Completed RCC works up to 32nd floor, 33rd floor RCC work in progress (80 % Completed).
Blockwork completed till 24th floor.
Plumbing Conceal work completed up to 23rd Floor.
Gypsum work completed up to 21st Floor.
Waterproofing completed up to 22nd Floor.
Electrical Conceal Work in blockwork completed up to 22nd Floor.
Door Frame fixing work completed up to 4th Floor.
Window rough ground marble fixing completed up to 21st Floor.
Window sill fixing completed up to 21st floor.
Tiling & dado completed in 195 Flats.
Kitchen Platform fixing completed in 195 Flats.
Lift Lobby Tiling completed of 2nd floor.
Elara Detailed updates (Possession – June 2023):
RCC work up to 35th floor completed., 36th floor RCC work in progress (20% Completed).
Blockwork completed till 29th floor.
Plumbing Conceal work completed up to 28th Floor.
Gypsum work completed up to 27th Floor.
Waterproofing completed up to 26th Floor.
Electrical Conceal Work in blockwork completed up to 27th Floor.
Door Frame fixing work completed up to 2nd Floor.
Window rough ground marble fixing completed up to 13th Floor.
Window sill fixing completed up to 13th floor.
Tiling & dado were completed on the 23rd floor.
Kitchen Platform fixing completed on 13th floor.
Lift Lobby Tiling work in progress of 9th floor . (70% Completed).