Construction Updates – October 2023

Update as on 6th October, 2023

Construction Updates – October 2023

Update as on 6th October, 2023

AURA - 1
AURA - 2
AURA - 3
ELARA - 1
ELARA - 2
NOVA
Tower Updates
AURA

Completed RCC Works up to the 36th Floor
LMR Bottom Slab Completed
LMR Tanks Completed
Block-work Completed Till the 36th Floor
Plumbing Conceal Work Completed up to the 36th Floor
Gypsum Work Completed up to the 36th Floor.
Waterproofing Completed up to the 36th Floor.
Electrical Conceal Work in Block-Work Completed up to 36th Floor
Door Frame Fixing Work Completed up to 33rd Floor.
Window Rough Ground Marble Fixing Completed up to 34rd Floor
Window Frame Fixing Upto 33rd Floor Completed
Window Glass Fixing Upto 33rd Floor Completed
Window Sill Fixing Completed up to the 34rd Floor
Tiling & Dado Were Completed up to the 35th Floor
Kitchen Platform Fixing Completed up to the 34th Floor
Lift Lobby Tiling Completed  Upto 34th Floor Complete
Staircase Tiling up to the 34th Floor Is Complete
1st Coat Painting Primer and Base Coat Putti Work Completed up to the 30th Floor.
2nd Coat Painting Primer and 2nd Coat Putti Work Completed up to the 30th Floor.
Internal Duct Finishing Completed
Service Slab Plaster Completed
External Plaster (95% Complete)
External Surface Preparation for Paint (95% Complete)
External Painting (95% Completed)
Fire Fighting Horizontal 1st to 36th Floor Completed
Fire Fighting Common Lobby Horizontal 1st to 36th Floor Completed
Fire Fighting Vertical Work Completed
Vertical Plumbing 95% Completed
Main Door Shutters Upto 31st Floor Completed
Bedroom Door Shutters Upto 31st Floor Completed
Electrical Wire Pulling Upto 31st Floor Completed
Electrical Switch Plate Upto 31st Floor Completed
Electrical Db Dressing Work Upto 25th Floor Completed
Electrical Substation 100% Completed
Electrical Meter Room 80% Completed
Lift Installation for Lift-1 Completed and Lift-2 Completed, Pwd NOC Received, Lift-3 and Lift-4 Installation 85% Completed.
Electrical and Fire Duct FRD Door Fixing Upto 25th Floor Completed,
Staircase FRD  Door Fixing  Upto 25th Floor Completed
Typical Lobby False Ceiling Framework Upto 25th Completed
Typical Lift Lobby Electrification Upto 17th Floor Completed
Courtyard Hydrant 90% Completed
Surrounding Infra 75% Completed
Fire Pumps and Panels 85% Completed
Rainwater Harvesting 75% Completed
STP 99% Completed
DG Sets With Connection 50% Completed
Solid Waste Compost Management Plant 75% Completed
Surrounds Plantation 25% Completed
Storm Water Drainage 95% Completed

ELARA

Completed RCC Works up to the 36th Floor
LMR Bottom Slab Completed
LMR Tanks Completed
Block-work Completed Till the 36th Floor
Plumbing Conceal Work Completed up to the 36th Floor
Gypsum Work Completed up to the 36th Floor
Waterproofing Completed up to the 36th Floor
Electrical Conceal Work in Block-Work Completed up to 36th Floor
Door Frame Fixing Work Completed up to 33rd Floor
Window Rough Ground Marble Fixing Completed up to 34rd Floor
Window Frame Fixing Upto 33rd Floor Completed
Window Glass Fixing Upto 33rd Floor Completed
Window Sill Fixing Completed up to the 34rd Floor
Tiling & Dado Were Completed up to the 35th Floor
Kitchen Platform Fixing Completed up to the 34th Floor
Lift Lobby Tiling Completed  Upto 34th Floor Complete
Staircase Tiling up to the 34th Floor Is Complete
1st Coat Painting Primer and Base Coat Putti Work Completed up to the 30th Floor.
2nd Coat Painting Primer and 2nd Coat Putti Work Completed up to the 30th Floor.
Internal Duct Finishing Completed
Service Slab Plaster Completed
External Plaster (95% Complete)
External Surface Preparation for Paint (95% Complete)
External Painting (95% Completed)
Fire Fighting Horizontal 1st to 36th Floor Completed
Fire Fighting Common Lobby Horizontal 1st to 36th Floor Completed
Fire Fighting Vertical Work Completed
Vertical Plumbing 95% Completed
Main Door Shutters Upto 31st Floor Completed
Bedroom Door Shutters Upto 31st Floor Completed
Electrical Wire Pulling Upto 31st Floor Completed
Electrical Switch Plate Upto 31st Floor Completed
Electrical Db Dressing Work Upto 25th Floor Completed
Electrical Substation 100% Completed
Electrical Meter Room 80% Completed
Lift Installation for Lift-1 Completed and Lift-2 Completed, Pwd NOC Received, Lift-3 and Lift-4 Installation 85% Completed.
Electrical and Fire Duct FRD Door Fixing Upto 25th Floor Completed,
Staircase FRD  Door Fixing  Upto 25th Floor Completed
Typical Lobby False Ceiling Framework Upto 25th Completed
Typical Lift Lobby Electrification Upto 17th Floor Completed
Courtyard Hydrant 90% Completed
Surrounding Infra 75% Completed
Fire Pumps and Panels 85% Completed
Rainwater Harvesting 75% Completed
STP 99% Completed
DG Sets With Connection 50% Completed
Solid Waste Compost Management Plant 75% Completed
Surrounds Plantation 25% Completed
Storm Water Drainage 95% Completed

NOVA RCC 12th Slab Completed
Excavation Work Completed
Foundation (Raft) Work Completed
Basement Work Complete
STP and UG Tanks Civil Work Completed
Plinth Slab Completed
Basement Surround Waterproofing and Backfilling Completed
Ground Floor Column Work Completed
Till 16th Slab Work Completed, 17th Slab Work in Progress(10% Completed)
Block-work on 1st Floor Completed 2nd – 9th Floor 85% Complete
Plumbing Conceal Work on the 1st Floor Completed. 2nd Floor Work in Progress.
Waterproofing on the 1st Floor Completed. 2nd Floor Work in Progress.
Gypsum Work Started On 1st to 6th Floors.
Surrounding Infra Work Started
Storm Water Drainage 30% Completed