Construction Updates – February 2023
Update as on 2nd February, 2023
Construction Updates – February 2023
Update as on 2nd February, 2023
Tower | Updates |
---|---|
Aura | RCC work up to 36th floor completed. Lift machine room bottom slab completed & tank 90% completed. Block work completed till 35th floor. Plumbing Conceal work completed up to 32nd Floor. Gypsum work completed up to 33rd Floor. Waterproofing completed up to 33rd Floor. Electrical Conceal Work in block-work completed up to 34th Floor. Door Frame fixing work completed up to 30th Floor. Window rough ground marble fixing completed up to 29th Floor. Window frames fixing 2nd to 25th floor completed. Window glass fixing 2nd to 20th floor completed, 21st to 25th floor 80% work completed. Window sill fixing completed up to 31st floor. Tiling & dado were completed up to the 32nd floor. Kitchen Platform fixing completed up to 32nd floor. Lift Lobby Tiling completed 1st to 30th-floor completed. Staircase tiling 2nd floor to 32nd floor completed. 1st coat painting primer and base coat putti work completed up to 27th floor. 2nd coat paiting primer & putti work completed upto 6th floor , 7th floor 80% completed. Internal Duct Finishing completed. Service slab Plaster completed. External Plaster (90% Complete) External surface preparation for paint (90% Complete) External painting ( 90% completed) Main door shutters 2nd to 25th floor completed. Bedroom door 2nd to 14th floor completed. Electrical wire pulling upto 6th floor completed, 7th floor 25% completed. Electrical switch plate 2nd to 5th floor completed, 6th floor 50% completed. Electrical DB work started. Electrical substation 100% completed. Electrical meter room 50% completed. Fire fighting common lobby horizontal 1st to 30th floor completed. Fire fighting vertical 1st to 36th floor completed. |
Elara | RCC work up to 36th floor completed. Block work completed till 36th floor. Lift machine room bottom slab completed. Terrace floor tank top completed. Plumbing Conceal work completed up to 35th Floor. Gypsum work completed up to 35th Floor. Waterproofing completed up to 35th Floor. Electrical Conceal Work in block-work completed up to 35th Floor. Door Frame fixing work completed up to 30th Floor. Window rough ground marble fixing completed up to 30th Floor. Window frames fixing 9th to 11th floor completed. Window glass fixing 9th to 11th floor work completed. Tiling & dado were completed on the 35th floor. Kitchen Platform fixing completed on 31st floor. Lift Lobby Tiling work completed on 2nd to 34th floor. Staircase tiling 2nd floor to 34th floor complete Painting primer and base coat putti work completed 2nd floor to 29th floor. Internal Duct Finishing (40% complete) Service slab Plaster (40% complete) External Plaster (40% Complete) External surface preparation for paint (75% Complete) Main door shutters 9th floor completed. Electrical substation 100% completed & meter room 10% completed. Fire fighting horizontal 9th to 25th floor completed & vertical 1st -36th floor work completed. |
Nova | Excavation work completed. Foundation raft work completed. Basement work completed. STP & UG tank civil work completed Plinth slab completed. Ground floor column work completed till 1st slab & 2nd slab work in progress ( 35% completed ) |
Marathon Referral and Loyalty Program
Refer your friends to any Marathon property and get rewards worth 1% of your friend’s flat cost. Your friend gets a discount too. It’s a win-win.