Construction Updates – January 2022
Update as on 1st January, 2022
Construction Updates – January 2022
Update as on 1st January, 2022
Tower | Updates |
---|---|
Aura | Detailed updates (Possession – Dec 2022): Completed RCC works up to 35th floor, 36th floor RCC work in progress (20 % Completed). Blockwork completed till 26th floor. Plumbing Conceal work completed up to 24th Floor. Gypsum work completed up to 23rd Floor. Waterproofing completed up to 24th Floor. Electrical Conceal Work in blockwork completed up to 23rd Floor. Door Frame fixing work completed up to 4th Floor. Window rough ground marble fixing completed up to 21st Floor. Window sill fixing completed up to 21st floor. Tiling & dado completed in 195 Flats. Kitchen Platform fixing completed in 195 Flats. Internal Painting base coat putty work Started. Lift Lobby Tiling completed of 2nd floor, 3rd floor & 4th floor work in progress ( 25% completed). |
Elara | Detailed updates (Possession – June 2023): RCC work up to 35th floor completed., 36th floor RCC work in progress (60% Completed). Blockwork completed till 32nd floor. Plumbing Conceal work completed up to 30th Floor. Gypsum work completed up to 28th Floor. Waterproofing completed up to 29th Floor. Electrical Conceal Work in blockwork completed up to 28th Floor. Door Frame fixing work completed up to 2nd Floor. Window rough ground marble fixing completed up to 13th Floor. Window sill fixing completed up to 13th floor. Tiling & dado were completed on the 27th floor. Kitchen Platform fixing completed on 19th floor. Internal Painting base coat putty work started. Lift Lobby Tiling work in progress of 9th floor . 10th & 11th floor work in progress (40% Completed). |