Construction Updates – July 2021
Construction Updates – July 2021
Tower | Updates |
---|---|
Aura | Detailed updates (Possession – July 2022): Completed RCC work upto 23rd floor, 24th floor RCC work in progress (90 % Completed). Blockwork completed till 21st floor.. Plumbing Conceal work completed upto 21st Floor. Gypsum work completed upto 21st Floor. Water proofing completed upto 21st Floor. Electrical Conceal Work in block work completed upto 21st Floor. Door Frame fixing work completed upto 4th Floor. Window rough ground marble fixing completed upto 21st Floor. Window sill fixing completed upto 21st floor. Tiling & dado completed in 195 Flats. Kitchen Platform fixing completed in 195 Flats. |
Elara | Detailed updates (Possession – December 2022): RCC work upto 24th floor completed., 25th floor RCC work in progress (40 % Completed). Blockwork completed till 15th floor. Plumbing Conceal work completed upto 10th Floor Gypsum work completed upto 10th Floor. Waterproofing completed upto 11th Floor. Electrical Conceal Work in block work completed upto 13th Floor. Door Frame fixing work completed upto 2nd Floor. Window rough ground marble fixing completed upto 2nd Floor. Window sill fixing completed upto 2nd floor. Tiling & dado completed upto 5th floor. |