Construction Updates – November 2021

Construction Updates – November 2021

AURA - 1
AURA - 2
AURA - 3
ELARA - 1
ELARA - 2
Tower Updates
Aura Detailed updates (Possession – Dec 2022):
Completed RCC work upto 31st floor , 32nd floor RCC work in progress (20% completed).
Blockwork completed till 22nd floor.
Plumbing Conceal work completed upto 21st Floor.
Gypsum work completed upto 21st Floor.
Waterproofing completed upto 21st Floor.
Electrical Conceal Work in block work completed upto 22nd Floor.
Door Frame fixing work completed upto 4th Floor.
Window rough ground marble fixing completed upto 21st Floor.
Window sill fixing completed upto 21st floor.
Tiling & dado completed in 195 Flats..
Kitchen Platform fixing completed in 195 Flats.
Elara Detailed updates (Possession – June 2023):
RCC work upto 33rd floor completed , 34th floor RCC work in progress (60% completed).
Blockwork completed till 26th floor.
Plumbing Conceal work completed upto 26th Floor.
Gypsum work completed upto 24th Floor.
Waterproofing completed upto 24th Floor.
Electrical Conceal Work in block work completed upto 25th Floor.
Door Frame fixing work completed upto 2nd Floor.
Window rough ground marble fixing completed upto 6th floor.
Window sill fixing completed upto 6th floor.
Tiling & dado completed on the 11th floor.
Kitchen Platform fixing completed on the 12th floor