Construction Updates – October 2022
Update as on 4th October, 2022
Construction Updates – October 2022
Update as on 4th October, 2022
Tower | Updates |
---|---|
Aura | RCC work up to 36th floor completed. Lift machine room bottom slab completed. Block work completed till 30th floor. Plumbing Conceal work completed up to 30th Floor. Gypsum work completed up to 30th Floor. Waterproofing completed up to 30th Floor. Electrical Conceal Work in block-work completed up to 30th Floor. Door Frame fixing work completed up to 27th Floor. Window rough ground marble fixing completed up to 27th Floor. Window frames fixing 2nd to 8th floor completed, 9th to 15th floor 50% work completed. Window glass fixing 2nd to 4th floor completed, 5th to 15th floor 25% work completed. Window sill fixing completed up to 27th floor. Tiling & dado were completed up to the 30th floor. Kitchen Platform fixing completed up to 28th floor. Lift Lobby Tiling completed 1st to 27th-floor complete, 28th & 29th-floor work in progress (90% Completed). Staircase tiling 2nd floor to 27th-floor complete, 28th-floor work in progress (90% Completed). Painting primer and base coat putti work completed up to 27th floor. Internal Duct Finishing (60% complete) Service slab Plaster (75% complete) External Plaster (55% Complete) External surface preparation for paint (50% Complete) External paiting ( 5% completed) |
Elara | RCC work up to 36th floor completed. Block work completed till 35th floor. Lift machine room bottom slab completed. Terrace floor tank top completed. Plumbing Conceal work completed up to 35th Floor. Gypsum work completed up to 34th Floor. Waterproofing completed up to 35th Floor. Electrical Conceal Work in block-work completed up to 35th Floor. Door Frame fixing work completed up to 30th Floor. Window rough ground marble fixing completed up to 30th Floor. Window sill fixing completed up to 30th floor. Window frames fixing 9th to 11th floor completed. Window glass fixing 9th to 11th floor work in progress. Tiling & dado were completed on the 34th floor. Kitchen Platform fixing completed on 31st floor. Lift Lobby Tiling work completed on 8th floor to 33rd floor. Staircase tiling 2nd floor to 34th floor complete Painting primer and base coat putti work completed 2nd floor to 29th floor. Internal Duct Finishing (15% complete) Service slab Plaster (75% complete) External Plaster (20% Complete) External surface preparation for paint (25% Complete) |
Nova | Excavation work completed. Basement work 65% completed. STP & UG tank civil work 90% completed Plinth slab 20% completed |
Marathon Referral and Loyalty Program
Refer your friends to any Marathon property and get rewards worth 1% of your friend’s flat cost. Your friend gets a discount too. It’s a win-win.