Construction Updates,
June 2021.

Zenith & Zodiac - Complete OC received

Altis, Avior, Acrux - OC till 24th Floor

Atlas and Aura - OC till 20th floor

ZENITH 100%
ZODIAC 100%
ACRUX 95%
ALTIS 95%
ANTILIA
20%
ATLAS 95%
ATRIA 70%
AURA 95%
AVIOR 95%
ION 70%
TRITON 70%
VEGA 70%
CEDAR
35%

% mentioned above is the current demand due as per the construction linked payment schedule

TOWER
FLOOR DETAILS
DETAILED UPDATES
Zenith
Completed
OC received
Zodiac
Completed
OC received
Acrux
Completed work up to Terrace slab level
Part OC received till 24th floor

RCC work complete till terrace slab

Flooring , Skirting , dado , kitchen platform, window roughground, toilet basin counter , plumbing work, water proofing , gypsumplaster, cement plaster, painting ,ms railing , Door frame ,Door shutter,door hardwares , Window , block work , flat alumium railing completed till the 31st floor

Door & shutter polish completed till the 24th floor & single coat polish done on above floors.

Cp & sanitary Flat completed till the 28th floor

Stair case – flooring & skirting completed till B2 To 31st floors

Stair case – window work completed till the terrace

Lift lobby flooring , Dado, Architrave , plaster, painting , flase ceiling ,door ,window work completed till the 31st floor

Entrance lobby work completed

Society office work completed

External Painting work completed till the 24 th floors & 25th to 31st 95% completed.

Terrace water proofing completed & flooring work done 70%

Concealed plumbing work completed from 1st to 31st floor

Fire fighting Delivery material & installation work completed B2 to 31st floor

Fire alarm work completed B2 to 31st floor. testing & commissioning completed

Lift completed from B2 to 31st floor ( 4 nos )
Ion
Completed work up to Terrace slab level
RCC completed till terrace floor


Conceal Plumbing work 4th to 30th floor 100% completed & 31st floor work in progress , kitchen platform 4th to 31st floor completed 1st &2nd floor work in progress ,door frames 4th to 13th & 16th floor completed , 14th,15th, &17th work in progress, block work toilet 4th floor to 28th floor 100% completed, 29th ,30th ,31st,1st &2nd work in progress

External painting putty, primer, texture base completed from basement 1 to terrace in flat 1 to 8 100% , final paint balance. Plumbing duct painting 80% and open duct work in progress


Lift 100% completed basement to 31st floor


Fire fighting installation 80% completed
Avior
Completed work up to Terrace slab level
Part OC received till 24th Floor

RCC work complete till terrace slab

Flat finishing work completed . Flooring , Skirting , dado , kitchen platform , window, toilet basin counter ,water proofing , gypsum plaster , cement plaster , painting , ms railing ,flat door frames this work done till the 31st floor

Stair case work completed from b2 to 31st floor

Entrance lobby work completed

Lift lobby completed till the 31st floor & painting work completed till 24th floor & 25th to 31st floor 1 coat paint balance

Refuge floor completed

Stilt floor work completed

Electrification service completed till 31st floor

Plumbing service completed in flat & servant toilet work completed till the 24th floor.

Fire fighting completed B2 to 31st floors & handover to facility

Lift all completed from B2 to 31st
Vega
Completed work up to Terrace slab level
RCC completed till terrace floor,

3rd floor to 30th floor conceal plumbing work completed 31st floor WIP

Water proofing 3rd to 20th floor completed above floor WIP

Block work 3rd to 30th floor completed

External painting texture work 65% completed

Lift 90% completed

Fire fighting installation 80 % completed 1st to 31st floor & lower , upper, & stilt floor fire 80% completed balance work in progress

Terrace water proofing 40% completed & balance work in progress
Antilia
Excavation completed
Foundation work 70% completed , plinth slab at 98.8mm level 10 % completed.
Aura
Completed work up to Terrace slab level
Part OC received till 20th floor

RCC work completed till terrace level

Possession flat 61 done

Flat finishing completed 100% 1st to 30th floor, flooring , kitchen platform , window , plumbing work , door fittings , flat aluminium railing

Painting work 1st to 20th 100% completed 21st to 30th floor 2nd coat in progress

External painting 1st to 30th floor 100% completed stilt painting 70% completed

Lift 100% completed L1 , L2, L3,L4 – Lb to 30th floor
Atlas
Completed work up to Terrace slab level
Part OC received till 20th floor

RCC completed till terrace floor

Flat finishing completed 100%

Possession flat – 71 done

External paintaing 1st to 30th floor completed stilt paintaing 80 % completed, duct & duct pipe paintaing completed 100%

Terrace water proofing completed & flooring work done 75%

Concealed plumbing completed 100%

Fire fighting installation b2 building from 1st to 30th floor completed B1 in progress

Lift 100% completed

Entrance lobby , society office , stair case , lift lobby completed 100%
Triton
Substructure RCC work completed
UGWT RCC completed

Superstructure RCC work below OHT bottom slab work completed , Parapet wall completed
Altis
Finishing work & RCC completed
RCC completed till terrace floor

Flat finishing work completed , Flooring,skirting, toilet flooring , toilet dado ,kitchen platform, window work completed till 100% , pplumbing work completed till 32nd floor 100% painting work done tiill 25th floor & 26th to 32nd floor 1st coat paint completed & 2 coat work in progress.

Door frame fixing work completed till 32nd floor 100% completed

Lift L1,L2.L3,L4 100% completed basement to 32nd floor

Fire fighting installation done till 32nd floor ,Fire alarm & testing ,commissioning done till 25th floor & 26th to 32nd floor 80% work completed
Cedar
Excavation completed
Substructure RCC work ground floor slab 103.75mm completed

UGWT completed

Superstructure RCC work 1st floor slab completed except open well staircase area mivan setting for 1st floor flat no 5,6,7 IP
Atria
RCC work completed
Substructure RCC work completed

UGWT , Superstructure RCC work , OHWT & LMR work completed