Construction Updates,
March 2021.

Zenith & Zodiac - Complete OC received

Altis, Avior, Acrux - OC till 24th Floor

Atlas and Aura - OC till 20th floor

ZENITH 100%
ZODIAC 100%
ACRUX 80%
ALTIS 90%
ANTILIA
20%
ATLAS 80%
ATRIA 70%
AURA 80%
AVIOR 90%
ION 70%
TRITON 70%
VEGA 70%
CEDAR
20%
TOWER
FLOOR DETAILS
DETAILED UPDATES
Zenith
Completed
OC received
Zodiac
Completed
OC received
Acrux
Completed work up to Terrace slab level
Part oc received till 24th floor

RCC work complete till terrace slab

1st to 31st floor tiling completed

Plumbing work in Completed upto 31st floor

Final coat paint 1st to 24th floor completed

Lift completed from B2 to 24th completed (3Nos), completed from B2 to 31st completed (1No)

Door frame fixing work completed till 31st floor
Ion
Completed work up to Terrace slab level
RCC completed till terrace floor


Conceal Plumbing completed up to 31st floor except 1st & 2nd floor, toilet water proofing complete upto 26th floor except 1st & 2nd floor, 75% external texture paint work completed

Door frame fixing work initiated form 4th floor


Kitchen Platform 3rd to 31st floor completed


3 lifts work completed ( L1, L2, & L4)
Avior
Completed work up to Terrace slab level
Part OC received till 24th Floor

RCC work complete till terrace slab

Internal Civil work completed

Internal Tiling work completed upto 31st floor except 27th floor

Toilet Conceal plumbing work completed upto 31st floor

Toilet waterproofing work completed upto 31st floor

Painting Completed B2 To 31st floor

Firefighting B2 to 31st floors are completed

All 4 lifts completed
Vega
Completed work up to Terrace slab level
RCC completed till terrace floor,

3rd floor to 23th floor Conceal plumbing work completed expect 1st & 2nd

Water proofing 3rd to 7th th Floor comleted 8th to 12th floor completed

1 lift is ready, 3 lift installation WIP

External texture paint work has initiated
Antilia
Foundation
Initiated work for foundation
Aura
Completed work up to Terrace slab level
OC received till 20th floor

RCC work completed till terrace level

Possession Done – 40 flats

Water proofing 1st floor to 30th floor work completed (Toilets & Kitchens Sunk) 27th to 30th floor utility and flower bed WIP

Tiling work Completed till 25th floor

All finishing activity completed upto 25th floor

Fire fighting, FAPA completed upto 30th floor

4 lifts work completed

Conceal plumbing work completed till the 25th floor
Atlas
Completed work up to Terrace slab level
OC received till 20th floor

Possession Done – 51 done

RCC work completed till terrace level

Tiling work Completed till 25th floor

All finishing activity completed upto 20th floor

Fire fighting, FAPA completed upto 30th floor

L-1,L-2, and L-4 LB to 30th floor 100% completed. L3 WIIP

Conceal plumbing work completed till the 25th floor
Triton
Completed RCC work up to 30th Slab level
RCC work completed up to 30th Slab level

25th Slab in progress. Pour 1 casting done. Pour 2 and pour 3 WIP.
Altis
Completed work up to Terrace slab level
1st Floor to Terrace Floor RCC work completed (33rd Floor Slab)

Part OC received till 24th Floor

Internal Civil work completed

Internal Tiling work initiated form 30th floor

Toilet waterproofing & conceal plumbing completed up to 31st floor

All 4 lifts completed

Entrance Lobby completed

External Painting Completed
Cedar
Excavation in progress
Substructure RCC work Ground Slap ( 103.75) completed