Construction Updates,
May 2023
Update as on 4th May 2023
Zenith & Zodiac - Complete OC received
Avior, Acrux ,Ion , Vega - OC till 30th Floor
Atlas and Aura - OC till 29th floor
Altis - OC till 31st floor
Phase 1
Phase 2
% mentioned above is the current demand due as per the construction linked payment schedule
OC received
OC received
Completed work up to Terrace slab level
OC received till 30th floor
Flat finishing work completed.
Common area finishing work completed.
Terrace water proofing completed .
Fire fighting & lift installation work completed.
Completed work up to Terrace slab level
OC received till 30th Floor.
RCC work complete till terrace slab.
Flat finishing work completed .
Common area finishing work completed.
Entrance lobby work completed
Lift lobby completed.
Refuge floor completed
Electrification service completed upto 31st floor.
Fire fighting work completed .
Lift all completed from B2 to 31st
Finishing work & RCC completed
OC received till 31st Floor.
Flat finishing work completed .
Lift & fire fighting installation work completed.
Completed work up to Terrace slab level
OC received till 29th floor
Flat finishing completed.
Possession flat handover started.
Common area finishing & External painting work completed.
Terrace water proofing completed.
Fire fighting installation & lift work completed.
Entrance lobby , society office , stair case & lift lobby completed .
Completed work up to Terrace slab level
OC received till 29th floor
Flat finishing completed.
Common area finishing & painting work completed.
Fire fighting & Lift installation work completed.
RCC work completed
Flat flooring work completed.
Kitchen Platform work completed.
Door frame completed.
Entrance lobby work completed.
External Painting completed.
Fire Fighting work completed.
Terrace water proofing completed.
Lift work completed.
D.G setup 98 % completed.
RCC work completed.
OC received till 30th Floor
Flat finishing work completed up to 31st floor.
Water proofing completed up to 31st floor.
External painting texture work completed.
Flat aluminium railing work completed.
Lift work & fire fighting installation work completed.
Terrace water proofing 100% complete
162 flat possession handover.
Completed work up to Terrace slab level
OC received till 30th Floor
Flat finishing work completed up to 31st floor.
External Painting completed.
Electrification service completed.
Lift 100% completed basement to 31st floor.
Terrace water proofing work 100% completed.
Fire fighting installed
possession handover for 123 flats
Superstructure RCC work completed up to terrace slab.
Substructure RCC work – Foundation , plinth slab stilt work 100% completed, 1st slab 100 % completed .
Superstructure RCC work completed up to terrace slab.
Substructure RCC work completed
Flat flooring work completed 95% & flower bed flooring completed from 2nd to 30th floor .
Toilet flooring completed from 1st to 30th floor.
External painting work completed 1st floor to terrace ( 90% )
Plumbing concealed work completed up to 30th floor.
Door frame making work completed till 30th floor.
Flat window work in progress, frame fixing completed from 2nd to 30th floor.
Tiling work in progress.
Fire fighting installation work 80% completed.
L1, L2 & L3 Lift handover and L3 lift fixing preparation work in progress up to 20th floor.
Superstructure RCC 28th slab completed
Substructure RCC Work Ground floor slab completed.
Superstructure RCC work completed up to 28th slab,
Block work completed up to 26th floor 100% completed & 27th floor work in progress.
Gypsum plaster completed upto 25th floor & above floor work in progress.
Cement plaster completed upto 25th floor.
Kitchen platform completed up to 15th floor .
Internal Plumbing work completed up to 26th floor expect down take .
Fire fighting installation work 65 % completed.
Superstructure RCC 26th floor slab casting completed
Superstructure RCC 26th slab casting completed & 27th pour reinforcement work in progress. (25% )
Plumbing work in progress.
Fire alarm installation of smoke detector work in progress on 20th floor.
Superstructure RCC 5th floor slab completed
Foundation work & Plinth slab completed.
Ground floor work 100% completed .
Superstructure RCC 6th floor slab completed, 7th slab in progress ( 95% )
Excavation work 100% completed.
Substructure RCC foundation 100% completed.
Column till LG 100 % completed.
Back filling till LG level completed 100% .
Grid slab work in progress. (100% completed)
Plinth checking completed.
Amenities work in progress
Swimming pool work 100% completed.
Kids play area 100% work completed.
Clubhouse work in progress.
TOWER | FLOOR DETAILS | DETAILED UPDATES |
---|---|---|
Zenith | Completed | OC received |
Zodiac | Completed | OC received |
Acrux | Completed work up to Terrace slab level | Part OC received till 24th floor
RCC work complete till terrace slab Flooring , Skirting , dado , kitchen platform, window roughground, toilet basin counter , plumbing work, water proofing , gypsumplaster, cement plaster, painting ,ms railing , Door frame ,Door shutter,door hardwares , Window , block work , flat alumium railing completed till the 31st floor Door & shutter polish completed till the 31st floor & single coat polish done on above floors. Cp & sanitary Flat completed till the 31st floor Stair case – flooring & skirting completed till B2 To 31st floors Stair case – window work completed till the terrace Lift lobby flooring , Dado, Architrave , plaster, painting , flase ceiling ,door ,window work completed till the 31st floor Entrance lobby work completed Society office work completed External Painting work completed till the 24 th floors & 25th to 31st 95% completed. Terrace water proofing completed & flooring work done 70% Concealed plumbing work completed from 1st to 31st floor Fire fighting Delivery material & installation work completed B2 to 31st floor Fire alarm work completed B2 to 31st floor. testing & commissioning completed Lift completed from B2 to 31st floor ( 4 nos ) |
Ion | Completed work up to Terrace slab level | RCC completed till terrace floor
Conceal Plumbing work 2nd to 31st floor 100% completed, kitchen platform 1st to 31st floor completed , door frames main door 1st to 31st and block work toilet 1st to 31st floor 100% completed External painting putty , primer, texture base completed from basement 1st to terrace in flat 01,02,05,06,07,08 100 % .Flat 3 & 4 work in progress Plumbing Duct & Open duct Painting-100% completed Lift 100% completed basement to 31st floor Fire fighting installation 100% completed |
Avior | Completed work up to Terrace slab level | Part OC received till 24th Floor
RCC work complete till terrace slab Flat finishing work completed . Flooring , Skirting , dado , kitchen platform , window, toilet basin counter ,water proofing , gypsum plaster , cement plaster , painting , ms railing ,flat door frames this work done till the 31st floor Stair case work completed from b2 to 31st floor Entrance lobby work completed Lift lobby completed till the 31st floor & painting work completed till 31st floor Refuge floor completed Stilt floor work completed Electrification service completed till 31st floor Plumbing service completed in flat & servant toilet work completed till the 31st floor. Fire fighting completed B2 to 31st floors & handover to facility Lift all completed from B2 to 31st |
Vega | Completed work up to Terrace slab level | RCC completed till terrace floor,
1st floor to 31st floor Conceal plumbing work completed Waterproofing 1st to 31st Floor completed 1st to 31st floor 100% completed (Ledge wall) External painting texture work 90% completed Lift 70% completed Fire fighting installation 100% completed, plinth slab 100% completed, testing and commissioning 100% completed Terrace water proofing 100% completed |
Antilia | Excavation completed | Foundation work 100% completed , plinth slab 100% completed. Stilt slab 100% completed , 1st Slab 100% completed |
Aura | Completed work up to Terrace slab level | Part OC received till 20th floor
RCC work completed till terrace level Possession flat 103 done Flat finishing completed 100% 1st to 30th floor, flooring , kitchen platform , window , plumbing work , door fittings , flat aluminium railing Painting work 1st to 30th 100% completed External painting 1st to 30th floor 100% completed stilt painting 85% completed Lift 100% completed L1 , L2, L3,L4 – Lb to 30th floor |
Atlas | Completed work up to Terrace slab level | Part OC received till 20th floor
RCC completed till terrace floor Flat finishing completed 100% Possession flat – 120 done External painting 1st to 30th floor completed, ventilation 100% completed, stilt painting 80 % completed, duct & duct pipe painting completed 100% Terrace water proofing completed & flooring work done 90% Concealed plumbing completed 100% Fire fighting installation B1 & b2 building from 1st to 30th floor completed Lift 100% completed Entrance lobby , society office , stair case , lift lobby completed 100% |
Triton | Substructure RCC work completed | UGWT RCC completed
Superstructure RCC work below OHT bottom slab work completed , Parapet wall completed |
Altis | Finishing work & RCC completed | RCC completed till terrace floor
Flat finishing work completed , Flooring, skirting, toilet flooring , toilet dado, kitchen platform, window work completed till 32nd floor, 100% painting work done till 25th floor and 26th to 32nd floor coat paint completed Door frame fixing work completed till 32nd floor 100% completed Lift L1,L2.L3,L4 100% completed basement to 32nd floor Fire fighting installation done till 32nd floor ,Fire alarm & testing ,commissioning done till 25th floor & 26th to 32nd floor 100% work completed |
Cedar | Excavation completed | Substructure RCC work ground floor slab 103.75mm completed
UGWT completed Superstructure RCC work upto 4th floor completed.5th floor 50% completed. |
Atria | RCC work completed | Substructure RCC work completed
Flat finishing work 5% completed , UGWT , Superstructure RCC work , OHWT & LMR work completed |
Marathon Referral and Loyalty Program
Refer your friends to any Marathon property and get rewards worth 1% of your friend’s flat cost. Your friend gets a discount too. It’s a win-win.