Construction Updates,
December 2021.
Update as on 6th December, 2021
Zenith & Zodiac - Complete OC received
Altis, Avior, Acrux - OC till 24th Floor
Atlas and Aura - OC till 20th floor
Phase 1
Phase 2
% mentioned above is the current demand due as per the construction linked payment schedule
OC received
OC received
Completed work up to Terrace slab level
Part OC received till 24th floor
RCC work complete till terrace slab
Flooring , Skirting , dado , kitchen platform, window roughground, toilet basin counter , plumbing work, water proofing , gypsumplaster, cement plaster, painting ,ms railing , Door frame ,Door shutter,door hardwares , Window , block work , flat alumium railing completed till the 31st floor
Door & shutter polish completed till the 31st floor & single coat polish done on above floors.
Cp & sanitary Flat completed till the 31st floor
Stair case – flooring & skirting completed till B2 To 31st floors
Stair case – window work completed till the terrace
Lift lobby flooring , Dado, Architrave , plaster, painting , flase ceiling ,door ,window work completed till the 31st floor
Entrance lobby work completed
Society office work completed
Terrace water proofing completed & flooring work done.
Concealed plumbing work completed from 1st to 31st floor
Fire fighting Delivery material & installation work completed B2 to 31st floor
Fire alarm work completed B2 to 31st floor. testing & commissioning completed
Lift completed from B2 to 31st floor ( 4 nos )
Completed work up to Terrace slab level
Part OC received till 24th Floor
RCC work complete till terrace slab
Flat finishing work completed . Flooring , Skirting , dado , kitchen platform , window, toilet basin counter ,water proofing , gypsum plaster , cement plaster , painting , ms railing ,flat door frames this work done till the 31st floor
Stair case work completed from b2 to 31st floor
Entrance lobby work completed
Lift lobby completed till the 31st floor & painting work completed till 31st floor
Refuge floor completed
Stilt floor work completed
Electrification service completed till 31st floor
Plumbing service completed in flat & servant toilet work completed till the 31st floor.
Fire fighting completed B2 to 31st floors & handover to facility
Lift all completed from B2 to 31st
Finishing work & RCC completed
RCC completed till terrace floor
Flat finishing work completed
Door frame fixing work completed till 32nd floor 100% completed
Lift L1,L2.L3,L4 100% completed basement to 32nd floor
Fire fighting installation done till 32nd floor completed
Completed work up to Terrace slab level
Part OC received till 20th floor
RCC completed till terrace floor
Flat finishing completed 100%
Possession flat – 120 done
External painting 1st to 30th floor completed, ventilation 100% completed stilt painting 80 % completed, duct & duct pipe painting completed 100%
Terrace water proofing completed & flooring work completed 90 %.
Concealed plumbing completed 100%
Fire fighting installation B1 & b2 building from 1st to 30th floor completed
Lift 100% completed
Entrance lobby , society office , stair case , lift lobby completed 100%
Completed work up to Terrace slab level
Part OC received till 20th floor
RCC work completed till terrace level
Possession flat 103 done
Flat finishing completed 100% 1st to 30th floor, flooring , kitchen platform , window , plumbing work , door fittings , flat aluminium railing
Painting work 1st to 30th 100% completed
External painting 1st to 30th floor 100% completed stilt painting 85% completed, duct & Duct pipe painting 100% completed.
Concealed plumbing work completed from 1st to 30th floor.
Lift 100% completed L1 , L2, L3,L4 – Lb to 30th floor
RCC work completed
Substructure RCC work completed
Expansion Joints 60 % work completed
Flat finishing flooring work 5% completed
UGWT , Superstructure RCC work , OHWT & LMR work completed
Completed work up to Terrace slab level
RCC completed till terrace floor
Conceal Plumbing work 1st to 31st floor 100% completed 1st floor work in progress ,Kitchen platform 1st to 31st floor completed, door frames main door 1st to 31st completed and block work toilet 1st to 31st floor 100% completed.
External Painting putty, primer, texture base Completed from basement 1 to terrace in flat 01,02,,05,06,07,08-100%. Flat 3&4 work in progress..
Plumbing Duct & Open duct Painting-100% completed
Lift 100% completed basement to 31st floor
Fire fighting installation 100% completed
Work up to Terrace slab level
RCC completed till terrace floor,
1st floor to 31st floor Conceal plumbing work completed.
Water proofing 1st to 31st floor completed
External painting texture work 90% completed
Lift 90% completed
Fire fighting installation,fire alarm ,testing & commissioning completed 100 %
Terrace water proofing 100% completed
Substructure RCC work completed
UGWT RCC completed
Superstructure RCC Work – Below OHT bottom Slab RCC work completed, parapet wall completed.
Excavation completed
Foundation work 100% completed, Plinth slab 100% completed, Stilt slab 100% completed, 1st slab 100% completed
Excavation completed
Substructure RCC Work – Ground floor slab(103.75m) completed.
Superstructure RCC work upto 4th floor completed-100%. 5th floor 50% completed
UGWT completed
Excavation completed
Footing completed
Tie beams (95.85m) level completed 100% Lower ground level 99.10m tie beams completed 100%
Column casting upto LG to GF casting work in progress. (40%)
Back-filling till LG level 100% completed.
Beam bottom work of GF slab work is in progress .
Construction not commenced yet
TOWER | FLOOR DETAILS | DETAILED UPDATES |
---|---|---|
Zenith | Completed | OC received |
Zodiac | Completed | OC received |
Acrux | Completed work up to Terrace slab level | Part OC received till 24th floor
RCC work complete till terrace slab Flooring , Skirting , dado , kitchen platform, window roughground, toilet basin counter , plumbing work, water proofing , gypsumplaster, cement plaster, painting ,ms railing , Door frame ,Door shutter,door hardwares , Window , block work , flat alumium railing completed till the 31st floor Door & shutter polish completed till the 31st floor & single coat polish done on above floors. Cp & sanitary Flat completed till the 31st floor Stair case – flooring & skirting completed till B2 To 31st floors Stair case – window work completed till the terrace Lift lobby flooring , Dado, Architrave , plaster, painting , flase ceiling ,door ,window work completed till the 31st floor Entrance lobby work completed Society office work completed External Painting work completed till the 24 th floors & 25th to 31st 95% completed. Terrace water proofing completed & flooring work done 70% Concealed plumbing work completed from 1st to 31st floor Fire fighting Delivery material & installation work completed B2 to 31st floor Fire alarm work completed B2 to 31st floor. testing & commissioning completed Lift completed from B2 to 31st floor ( 4 nos ) |
Ion | Completed work up to Terrace slab level | RCC completed till terrace floor
Conceal Plumbing work 2nd to 31st floor 100% completed, kitchen platform 1st to 31st floor completed , door frames main door 1st to 31st and block work toilet 1st to 31st floor 100% completed External painting putty , primer, texture base completed from basement 1st to terrace in flat 01,02,05,06,07,08 100 % .Flat 3 & 4 work in progress Plumbing Duct & Open duct Painting-100% completed Lift 100% completed basement to 31st floor Fire fighting installation 100% completed |
Avior | Completed work up to Terrace slab level | Part OC received till 24th Floor
RCC work complete till terrace slab Flat finishing work completed . Flooring , Skirting , dado , kitchen platform , window, toilet basin counter ,water proofing , gypsum plaster , cement plaster , painting , ms railing ,flat door frames this work done till the 31st floor Stair case work completed from b2 to 31st floor Entrance lobby work completed Lift lobby completed till the 31st floor & painting work completed till 31st floor Refuge floor completed Stilt floor work completed Electrification service completed till 31st floor Plumbing service completed in flat & servant toilet work completed till the 31st floor. Fire fighting completed B2 to 31st floors & handover to facility Lift all completed from B2 to 31st |
Vega | Completed work up to Terrace slab level | RCC completed till terrace floor,
1st floor to 31st floor Conceal plumbing work completed Waterproofing 1st to 31st Floor completed 1st to 31st floor 100% completed (Ledge wall) External painting texture work 90% completed Lift 70% completed Fire fighting installation 100% completed, plinth slab 100% completed, testing and commissioning 100% completed Terrace water proofing 100% completed |
Antilia | Excavation completed | Foundation work 100% completed , plinth slab 100% completed. Stilt slab 100% completed , 1st Slab 100% completed |
Aura | Completed work up to Terrace slab level | Part OC received till 20th floor
RCC work completed till terrace level Possession flat 103 done Flat finishing completed 100% 1st to 30th floor, flooring , kitchen platform , window , plumbing work , door fittings , flat aluminium railing Painting work 1st to 30th 100% completed External painting 1st to 30th floor 100% completed stilt painting 85% completed Lift 100% completed L1 , L2, L3,L4 – Lb to 30th floor |
Atlas | Completed work up to Terrace slab level | Part OC received till 20th floor
RCC completed till terrace floor Flat finishing completed 100% Possession flat – 120 done External painting 1st to 30th floor completed, ventilation 100% completed, stilt painting 80 % completed, duct & duct pipe painting completed 100% Terrace water proofing completed & flooring work done 90% Concealed plumbing completed 100% Fire fighting installation B1 & b2 building from 1st to 30th floor completed Lift 100% completed Entrance lobby , society office , stair case , lift lobby completed 100% |
Triton | Substructure RCC work completed | UGWT RCC completed
Superstructure RCC work below OHT bottom slab work completed , Parapet wall completed |
Altis | Finishing work & RCC completed | RCC completed till terrace floor
Flat finishing work completed , Flooring, skirting, toilet flooring , toilet dado, kitchen platform, window work completed till 32nd floor, 100% painting work done till 25th floor and 26th to 32nd floor coat paint completed Door frame fixing work completed till 32nd floor 100% completed Lift L1,L2.L3,L4 100% completed basement to 32nd floor Fire fighting installation done till 32nd floor ,Fire alarm & testing ,commissioning done till 25th floor & 26th to 32nd floor 100% work completed |
Cedar | Excavation completed | Substructure RCC work ground floor slab 103.75mm completed
UGWT completed Superstructure RCC work upto 4th floor completed.5th floor 50% completed. |
Atria | RCC work completed | Substructure RCC work completed
Flat finishing work 5% completed , UGWT , Superstructure RCC work , OHWT & LMR work completed |