Construction Updates,
July 2022

Update as on 6th July, 2022

Zenith & Zodiac - Complete OC received

Altis, Avior, Acrux - OC till 24th Floor

Atlas and Aura - OC till 20th floor

Phase 1

ZENITH 100%
ZODIAC 100%
ACRUX 95%
ALTIS 95%
ANTILIA
50%
ATLAS 95%
ATRIA 86%
AURA 95%
AVIOR 95%
ION 95%
TRITON 70%
VEGA 95%

Phase 2

CEDAR
70%
DAFFODIL
35%
BODHI
35%

% mentioned above is the current demand due as per the construction linked payment schedule

OC received

OC received

Completed work up to Terrace slab level

Part OC received till 24th floor

RCC work complete till terrace slab

Flat finishing work completed.

Common area finishing work completed.

Stair case work completed.

Entrance lobby work completed

Terrace water proofing completed & flooring work done.

Concealed plumbing work completed upto 31st floor.

Fire fighting work completed.

Lift work completed.

Completed work up to Terrace slab level

Part OC received till 24th Floor

RCC work complete till terrace slab

Flat finishing work completed . 

Common area finishing work completed.

Entrance lobby work completed

Lift lobby completed.

Refuge floor completed

Electrification service completed upto 31st floor.

Fire fighting work completed .

Lift all completed from B2 to 31st

Finishing work & RCC completed

RCC completed till terrace floor

Flat finishing work completed 

Door frame fixing work completed till 32nd floor 100% completed

Lift work completed.

Fire fighting installation done upto 32nd floor completed

Completed work up to Terrace slab level

Part OC received till 20th floor

RCC completed till terrace floor

Flat finishing completed 100%

Possession flat – 153 done

External painting completed.

Common area finishing work completed.

Terrace water proofing completed.

Concealed plumbing completed .

Fire fighting installated.

Lift work completed

Entrance lobby , society office , stair case & lift lobby completed 

Completed work up to Terrace slab level

Part OC received till 20th floor

RCC work completed till terrace level

Possession flat handover overall 141 nos

Flat finishing completed.

Common area finishing work completed.

Painting work completed upto 30th floor.

Fire fighting work completed upto 30th floor.

Lift work completed.

RCC work completed

Flat flooring work completed.

Kitchen Platform work  completed upto 29th floor.

Internal door frame completed upto 25th floor & Main door frame completed upto 28th floor . 

External Painting south work completed.

Fire Fighting work completed.

Terrace water proofing work in progress .

Lift work completed.

Work up to Terrace slab level

RCC completed till terrace floor.

1st floor to 31st floor Conceal plumbing work completed.

Door frame work completed.

Water proofing completed upto 31st floor.

External painting texture work completed.

Flat aluminium railing completed upto 31st floor.

Lift work completed.

Concealed plumbing completed upto 31st floor.

Fire fighting installation completed 100 %

Terrace water proofing 100% complete

Completed work up to Terrace slab level

RCC completed till terrace floor

Conceal Plumbing , Kitchen platform, Door frames and Block work completed upto 31st floor.

External Painting completed.

Door & shutter polish work 1st to 31st floor 100% completed.


Lift 100% completed basement to 31st floor.

Flat window work completed.

Flat aluminium railing completed upto 31st floor.

Terrace water proofing work 100% completed.


Fire fighting installed

Excavation completed

Foundation work, Plinth slab & Stilt slab 100% completed.

Under ground water tank of RCC work completed.

Superstructure RCC work- 9th slab 100% completed.

Substructure RCC work completed

UGWT RCC completed

Superstructure RCC Work 100% completed.

Gypsum plaster 75% completed.

External painting work in progress.

Internal Plumbing 30% completed.

Door frame making work in progress.

Tiling work in progress.

Lift installation work in progress.

Excavation completed

Substructure RCC Work  –  Ground floor slab ( 103.75m) completed.

Superstructure RCC work upto 22nd slab completed-100%. 23rd slab 66 % completed

Under ground water tank ( UGWT ) completed.

 

Excavation completed

Footing completed

Substructure work – Plinth checking is done.

1st slab completed & 2nd mivan setting slab in progress

Under ground water tank work 100 % completed.

Excavation 100% done

Foundation work 100% completed.
Plinth slab 100% completed

TOWER
FLOOR DETAILS
DETAILED UPDATES
Zenith
Completed
OC received
Zodiac
Completed
OC received
Acrux
Completed work up to Terrace slab level
Part OC received till 24th floor

RCC work complete till terrace slab

Flooring , Skirting , dado , kitchen platform, window roughground, toilet basin counter , plumbing work, water proofing , gypsumplaster, cement plaster, painting ,ms railing , Door frame ,Door shutter,door hardwares , Window , block work , flat alumium railing completed till the 31st floor

Door & shutter polish completed till the 31st floor & single coat polish done on above floors.

Cp & sanitary Flat completed till the 31st floor

Stair case – flooring & skirting completed till B2 To 31st floors

Stair case – window work completed till the terrace

Lift lobby flooring , Dado, Architrave , plaster, painting , flase ceiling ,door ,window work completed till the 31st floor

Entrance lobby work completed

Society office work completed

External Painting work completed till the 24 th floors & 25th to 31st 95% completed.

Terrace water proofing completed & flooring work done 70%

Concealed plumbing work completed from 1st to 31st floor

Fire fighting Delivery material & installation work completed B2 to 31st floor

Fire alarm work completed B2 to 31st floor. testing & commissioning completed

Lift completed from B2 to 31st floor ( 4 nos )
Ion
Completed work up to Terrace slab level
RCC completed till terrace floor



Conceal Plumbing work 2nd to 31st floor 100% completed, kitchen platform 1st to 31st floor completed , door frames main door 1st to 31st and block work toilet 1st to 31st floor 100% completed

External painting putty , primer, texture base completed from basement 1st to terrace in flat 01,02,05,06,07,08 100 % .Flat 3 & 4 work in progress

Plumbing Duct & Open duct Painting-100% completed


Lift 100% completed basement to 31st floor


Fire fighting installation 100% completed
Avior
Completed work up to Terrace slab level
Part OC received till 24th Floor

RCC work complete till terrace slab

Flat finishing work completed . Flooring , Skirting , dado , kitchen platform , window, toilet basin counter ,water proofing , gypsum plaster , cement plaster , painting , ms railing ,flat door frames this work done till the 31st floor

Stair case work completed from b2 to 31st floor

Entrance lobby work completed

Lift lobby completed till the 31st floor & painting work completed till 31st floor

Refuge floor completed

Stilt floor work completed

Electrification service completed till 31st floor

Plumbing service completed in flat & servant toilet work completed till the 31st floor.

Fire fighting completed B2 to 31st floors & handover to facility

Lift all completed from B2 to 31st
Vega
Completed work up to Terrace slab level
RCC completed till terrace floor,

1st floor to 31st floor Conceal plumbing work completed

Waterproofing 1st to 31st Floor completed

1st to 31st floor 100% completed (Ledge wall)

External painting texture work 90% completed

Lift 70% completed

Fire fighting installation 100% completed, plinth slab 100% completed, testing and commissioning 100% completed

Terrace water proofing 100% completed
Antilia
Excavation completed
Foundation work 100% completed , plinth slab 100% completed. Stilt slab 100% completed , 1st Slab 100% completed
Aura
Completed work up to Terrace slab level
Part OC received till 20th floor

RCC work completed till terrace level

Possession flat 103 done

Flat finishing completed 100% 1st to 30th floor, flooring , kitchen platform , window , plumbing work , door fittings , flat aluminium railing

Painting work 1st to 30th 100% completed

External painting 1st to 30th floor 100% completed stilt painting 85% completed

Lift 100% completed L1 , L2, L3,L4 – Lb to 30th floor
Atlas
Completed work up to Terrace slab level
Part OC received till 20th floor

RCC completed till terrace floor

Flat finishing completed 100%

Possession flat – 120 done

External painting 1st to 30th floor completed, ventilation 100% completed, stilt painting 80 % completed, duct & duct pipe painting completed 100%

Terrace water proofing completed & flooring work done 90%

Concealed plumbing completed 100%

Fire fighting installation B1 & b2 building from 1st to 30th floor completed

Lift 100% completed

Entrance lobby , society office , stair case , lift lobby completed 100%
Triton
Substructure RCC work completed
UGWT RCC completed

Superstructure RCC work below OHT bottom slab work completed , Parapet wall completed
Altis
Finishing work & RCC completed
RCC completed till terrace floor

Flat finishing work completed , Flooring, skirting, toilet flooring , toilet dado, kitchen platform, window work completed till 32nd floor, 100% painting work done till 25th floor and 26th to 32nd floor coat paint completed

Door frame fixing work completed till 32nd floor 100% completed

Lift L1,L2.L3,L4 100% completed basement to 32nd floor

Fire fighting installation done till 32nd floor ,Fire alarm & testing ,commissioning done till 25th floor & 26th to 32nd floor 100% work completed
Cedar
Excavation completed
Substructure RCC work ground floor slab 103.75mm completed

UGWT completed

Superstructure RCC work upto 4th floor completed.5th floor 50% completed.
Atria
RCC work completed
Substructure RCC work completed

Flat finishing work 5% completed , UGWT , Superstructure RCC work , OHWT & LMR work completed

Marathon Referral and Loyalty Program

Refer your friends to any Marathon property and get rewards worth 1% of your friend’s flat cost. Your friend gets a discount too. It’s a win-win.