Construction Updates,
October 2021.
Zenith & Zodiac - Complete OC received
Altis, Avior, Acrux - OC till 24th Floor
Atlas and Aura - OC till 20th floor
Phase 1
Phase 2
% mentioned above is the current demand due as per the construction linked payment schedule
OC received
OC received
Completed work up to Terrace slab level
Part OC received till 24th floor
RCC work complete till terrace slab
Flooring , Skirting , dado , kitchen platform, window roughground, toilet basin counter , plumbing work, water proofing , gypsumplaster, cement plaster, painting ,ms railing , Door frame ,Door shutter,door hardwares , Window , block work , flat alumium railing completed till the 31st floor
Door & shutter polish completed till the 31st floor & single coat polish done on above floors.
Cp & sanitary Flat completed till the 31st floor
Stair case – flooring & skirting completed till B2 To 31st floors
Stair case – window work completed till the terrace
Lift lobby flooring , Dado, Architrave , plaster, painting , flase ceiling ,door ,window work completed till the 31st floor
Entrance lobby work completed
Society office work completed
External Painting work completed till the 24 th floors & 25th to 31st 95% completed. Duct & duct painting completed 95 %.
Terrace water proofing completed & flooring work done.
Concealed plumbing work completed from 1st to 31st floor
Fire fighting Delivery material & installation work completed B2 to 31st floor
Fire alarm work completed B2 to 31st floor. testing & commissioning completed
Lift completed from B2 to 31st floor ( 4 nos )
Completed work up to Terrace slab level
RCC completed till terrace floor
Conceal Plumbing work 2nd to 31st floor 100% completed,Kitchen platform 1st to 31st floor completed, door frames main door 1st to 31st and internal flat 2nd to 23rd floor completed and 1st to 21st floor WIP, block work toilet 1st to 31st floor 100% completed.
External Painting putty, primer, texture base Completed from basement 1 to terrace in flat 01,02,,05,06,07,08-100%. Flat 3&4 work in progress.
Plumbing Duct & Open duct Painting-100% completed
Lift 100% completed basement to 31st floor
Fire fighting installation 100% completed
Completed work up to Terrace slab level
Part OC received till 24th Floor
RCC work complete till terrace slab
Flat finishing work completed . Flooring , Skirting , dado , kitchen platform , window, toilet basin counter ,water proofing , gypsum plaster , cement plaster , painting , ms railing ,flat door frames this work done till the 31st floor
Stair case work completed from b2 to 31st floor
Entrance lobby work completed
Lift lobby completed till the 31st floor & painting work completed till 31st floor
Refuge floor completed
Stilt floor work completed
Electrification service completed till 31st floor
Plumbing service completed in flat & servant toilet work completed till the 31st floor.
Fire fighting completed B2 to 31st floors & handover to facility
Lift all completed from B2 to 31st
Completed work up to Terrace slab level
RCC completed till terrace floor,
1st floor to 31st floor Conceal plumbing work completed.
Waterproofing 1st to 31st Floor completed, 29th floor WIP.
External painting texture work 85% completed
Lift 90% completed
Fire fighting installation 100% completed, plinth slab 100% completed, testing and commissioning 100% completed
Terrace water proofing 40% completed & balance work in progress
Excavation completed
Foundation work 100% completed, plinth slab 100% completed. UGWT 100% RCC Completed.
Completed work up to Terrace slab level
Part OC received till 20th floor
RCC work completed till terrace level
Possession flat 83 done
Flat finishing completed 100% 1st to 30th floor, flooring , kitchen platform , window , plumbing work , door fittings , flat aluminium railing
Painting work 1st to 30th 100% completed
External painting 1st to 30th floor 100% completed. Stilt painting 85% completed.
Concealed plumbing work completed from 1st to 30th floor.
Lift 100% completed L1 , L2, L3,L4 – Lb to 30th floor
Completed work up to Terrace slab level
Part OC received till 20th floor
RCC completed till terrace floor
Flat finishing completed 100%
Possession flat – 96 done
External painting 1st to 30th floor completed, ventilation 100% completed, stilt painting 80 % completed, duct & duct pipe painting completed 100%
Terrace water proofing completed & flooring work completed 100 %.
Concealed plumbing completed 100%
Fire fighting installation B1 & b2 building from 1st to 30th floor completed
Lift 100% completed
Entrance lobby , society office , stair case , lift lobby completed 100%
Substructure RCC work completed
UGWT RCC completed
Superstructure RCC Work – Below OHT bottom Slab RCC work completed, parapet wall completed.
Finishing work & RCC completed
RCC completed till terrace floor
Flat finishing work completed , Flooring, skirting, toilet flooring , toilet dado, kitchen platform, window work completed till 32nd floor, 100% painting work done till 25th floor and 26th to 32nd floor coat paint completed
Door frame fixing work completed till 32nd floor 100% completed
Lift L1,L2.L3,L4 100% completed basement to 32nd floor
Fire fighting installation done till 32nd floor ,Fire alarm & testing ,commissioning done till 25th floor & 26th to 32nd floor 100% work completed
Excavation completed
Substructure RCC Work – Ground floor slab(103.75m) completed.
Superstructure RCC work upto 3rd floor completed-100%.
4th floor flat no. 5,6,7 competed
RCC work completed
Substructure RCC work completed
UGWT , Superstructure RCC work , OHWT & LMR work completed
Excavation completed
Footing completed
Column casting completed upto tie beam level
Column casting upto LG level is done 20%
Back-filling and levelling is in progress
UG tank pardi casted upto tie beam level. 2nd layer pardi reinforcement work is in progress
TOWER | FLOOR DETAILS | DETAILED UPDATES |
---|---|---|
Zenith | Completed | OC received |
Zodiac | Completed | OC received |
Acrux | Completed work up to Terrace slab level | Part OC received till 24th floor
RCC work complete till terrace slab Flooring , Skirting , dado , kitchen platform, window roughground, toilet basin counter , plumbing work, water proofing , gypsumplaster, cement plaster, painting ,ms railing , Door frame ,Door shutter,door hardwares , Window , block work , flat alumium railing completed till the 31st floor Door & shutter polish completed till the 31st floor & single coat polish done on above floors. Cp & sanitary Flat completed till the 31st floor Stair case – flooring & skirting completed till B2 To 31st floors Stair case – window work completed till the terrace Lift lobby flooring , Dado, Architrave , plaster, painting , flase ceiling ,door ,window work completed till the 31st floor Entrance lobby work completed Society office work completed External Painting work completed till the 24 th floors & 25th to 31st 95% completed. Terrace water proofing completed & flooring work done 70% Concealed plumbing work completed from 1st to 31st floor Fire fighting Delivery material & installation work completed B2 to 31st floor Fire alarm work completed B2 to 31st floor. testing & commissioning completed Lift completed from B2 to 31st floor ( 4 nos ) |
Ion | Completed work up to Terrace slab level | RCC completed till terrace floor
Conceal Plumbing work 2nd to 31st floor 100% completed, kitchen platform 4th to 31st floor completed 1st & 2nd floor work in progress, door frames main door 1st to 31st and internal flat 2nd to 23rd floor completed and 1st to 21st floor WIP, block work toilet 1st to 31st floor 100% completed Painting 4th to 9th floor putty work completed & 10th floor WIP Plumbing Duct & Open duct Painting-100% completed Lift 100% completed basement to 31st floor Fire fighting installation 100% completed |
Avior | Completed work up to Terrace slab level | Part OC received till 24th Floor
RCC work complete till terrace slab Flat finishing work completed . Flooring , Skirting , dado , kitchen platform , window, toilet basin counter ,water proofing , gypsum plaster , cement plaster , painting , ms railing ,flat door frames this work done till the 31st floor Stair case work completed from b2 to 31st floor Entrance lobby work completed Lift lobby completed till the 31st floor & painting work completed till 31st floor Refuge floor completed Stilt floor work completed Electrification service completed till 31st floor Plumbing service completed in flat & servant toilet work completed till the 31st floor. Fire fighting completed B2 to 31st floors & handover to facility Lift all completed from B2 to 31st |
Vega | Completed work up to Terrace slab level | RCC completed till terrace floor,
1st floor to 31st floor Conceal plumbing work completed 1st work in progress Waterproofing 1st to 28th Floor completed and 29th floor WIP 3rd to 31st floor 100% completed (Ledge wall) External painting texture work 80% completed Lift 90% completed Fire fighting installation 100% completed, plinth slab 100% completed, testing and commissioning 100% completed Terrace water proofing 40% completed & balance work in progress |
Antilia | Excavation completed | Foundation work 100% completed , plinth slab 100% completed. UGWT 100% RCC Completed |
Aura | Completed work up to Terrace slab level | Part OC received till 20th floor
RCC work completed till terrace level Possession flat 82 done Flat finishing completed 100% 1st to 30th floor, flooring , kitchen platform , window , plumbing work , door fittings , flat aluminium railing Painting work 1st to 30th 100% completed External painting 1st to 30th floor 100% completed stilt painting 80% completed Lift 100% completed L1 , L2, L3,L4 – Lb to 30th floor |
Atlas | Completed work up to Terrace slab level | Part OC received till 20th floor
RCC completed till terrace floor Flat finishing completed 100% Possession flat – 94 done External painting 1st to 30th floor completed, ventilation 100% completed, stilt painting 80 % completed, duct & duct pipe painting completed 100% Terrace water proofing completed & flooring work done 90% Concealed plumbing completed 100% Fire fighting installation B1 & b2 building from 1st to 30th floor completed Lift 100% completed Entrance lobby , society office , stair case , lift lobby completed 100% |
Triton | Substructure RCC work completed | UGWT RCC completed
Superstructure RCC work below OHT bottom slab work completed , Parapet wall completed |
Altis | Finishing work & RCC completed | RCC completed till terrace floor
Flat finishing work completed , Flooring, skirting, toilet flooring , toilet dado, kitchen platform, window work completed till 32nd floor, 100% painting work done till 25th floor and 26th to 32nd floor coat paint completed Door frame fixing work completed till 32nd floor 100% completed Lift L1,L2.L3,L4 100% completed basement to 32nd floor Fire fighting installation done till 32nd floor ,Fire alarm & testing ,commissioning done till 25th floor & 26th to 32nd floor 100% work completed |
Cedar | Excavation completed | Substructure RCC work ground floor slab 103.75mm completed
UGWT completed Superstructure RCC work 1st floor completed 2nd floor conventional area-100% completed, 3rd floor flat no. 4, 5, 6 completed |
Atria | RCC work completed | Substructure RCC work completed
UGWT , Superstructure RCC work , OHWT & LMR work completed |