Construction Updates, August 2023

Update as on 5th August, 2023

Construction Updates, August 2023

Update as on 5th August, 2023

Zaver Aracde
70%

% mentioned above is the current demand due as per the construction linked payment schedule.

Floor Details Detailed Updates

Substructure RCC Work

100 % completed.

Superstructure RCC Work

Terrace slab completed.

Shop Finishing

Flooring, Skirting, Gypsum plaster, Cement plaster, Block work 100 % completed.

Common Area Finishing

1st floor stair case flooring & skirting work 100% completed.
Blockwork completed till 15th floor.
Water proofing completed till 13th floor.
DG set installation work completed
Habitable Fire fighting work completed till 9th floor.
Car lift 90% installation completed.
Entrance lobby flooring ,dodo & facade work 100% completed.
Gypsum work completed till 12th floor .